IP69K Hygienic Stainless Food Delta Robot
Product family: Washdown Pick-and-Place Arms.
Flow: Carbon Rods & 316L Cast → 316L Base Electropolish → Carbon Arm Ball-Joint Epoxy → Direct-Drive Servo Seal Fit → 2D Vision Belt Sync Calib → 90-Pick/Min Washdown Run → Food & Bakery Pack Lines
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. 316L Base Electropolish | 1,350 s | 25 min | 94% | 98.4% | 22 | 50 (1.79 d) | 36 |
| 2. Carbon Arm Ball-Joint Epoxy | 1,620 s | 20 min | 92% | 97.2% | 11 | 42 (1.50 d) | 28 |
| 3. Direct-Drive Servo Seal Fit | 2,064 s | 30 min | 85% | 94.8% | 14 | 56 (2.00 d) | 20 |
| 4. 2D Vision Belt Sync Calib | 1,466 s | 12 min | 95% | 98.0% | 7 | 28 (1.00 d) | 32 |
| 5. 90-Pick/Min Washdown Run | 1,119 s | 10 min | 97% | 99.1% | 4 | 20 (0.71 d) | 43 |
Key figures
- Takt time
- 1,929 s
- Lead time
- 8.36 d
- Value-added time
- 7,619 s
- Process cycle efficiency (PCE)
- 1.7%
- Rolled throughput yield (RTY)
- 88.1%
- Customer demand per day
- 28 units
- Line capacity per day
- 20 units
- Bottleneck
- Direct-Drive Servo Seal Fit
Reading the bottleneck
The bottleneck is "Direct-Drive Servo Seal Fit": it can process 20 units per day against a demand of 28 units, so it falls short of demand by 29.7%. Once downtime and scrap are counted, its cycle time grows from 2,064 s to 2,561 s, against a takt of 1,929 s. The largest loss at this step is equipment downtime (uptime 85%), about 364 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Robotics, Automation & Additive 3D: Robotics, Automation & Additive 3D
- 6-Axis Collaborative Robot (Cobot) Line
- Quad-Laser Titanium LPBF Additive Cell
- 1.5T SLAM Lidar Autonomous Mobile Robot
- End-of-Line High-Speed Robotic Palletizer Cell
- High-Speed 6m Linear Motor Pick Gantry
- Scanner-Guided 6kW Remote Laser Welding Head
- EFEM Cleanroom Dual-Blade Wafer Handler
- 12-Station Servo CNC Tool Changer Turret
- High-Volume Metal Binder-Jet 3D Print Line
- AI Hyperspectral Optical Food & Plastic Sorter
- Multilevel Warehouse AS/RS Rail Shuttle