Quad-Laser Titanium LPBF Additive Cell

Product family: LPBF Aerospace & Med Parts.

Flow: Additive powder supplier → Build-Plate Level & Argon → Quad-Laser 60um Melt Cycle → Wire-EDM Cut & Powder Sieve → Hot Isostatic Press (HIP) → CT-Scan Pore & Tensile Test → MedTech & Aero Clients

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Quad-Laser Titanium LPBF Additive CellSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Additive powder supplier → Build-Plate Level & Argon (515 s) → Quad-Laser 60um Melt Cycle (619 s) → Wire-EDM Cut & Powder Sieve (788 s) → Hot Isostatic Press (HIP) (560 s) → CT-Scan Pore & Tensile Test (427 s) → MedTech & Aero Clients.SUPPLIERAdditive powdersupplierI1.80 d1Build-Plate Level& ArgonC/T 515 sI1.50 d2Quad-Laser 60umMelt CycleC/T 619 sI2.00 d3Wire-EDM Cut &Powder SieveC/T 788 sI1.00 d4Hot IsostaticPress (HIP)C/T 560 sI0.70 d5CT-Scan Pore &Tensile TestC/T 427 sI1.20 dCUSTOMERMedTech & AeroClients110 / parts

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Build-Plate Level & Argon515 s25 min94%98.4%88198 (1.80 d)142
2. Quad-Laser 60um Melt Cycle619 s20 min92%97.2%44165 (1.50 d)113
3. Wire-EDM Cut & Powder Sieve788 s30 min85%94.8%55220 (2.00 d)79
4. Hot Isostatic Press (HIP)560 s12 min95%98.0%28110 (1.00 d)130
5. CT-Scan Pore & Tensile Test427 s10 min97%99.1%1777 (0.70 d)174

Key figures

Takt time
736 s
Lead time
8.24 d
Value-added time
2,909 s
Process cycle efficiency (PCE)
0.44%
Rolled throughput yield (RTY)
88.1%
Customer demand per day
110 parts
Line capacity per day
79 parts
Bottleneck
Wire-EDM Cut & Powder Sieve

Reading the bottleneck

The bottleneck is "Wire-EDM Cut & Powder Sieve": it can process 79 parts per day against a demand of 110 parts, so it falls short of demand by 28.0%. Once downtime and scrap are counted, its cycle time grows from 788 s to 978 s, against a takt of 736 s. The largest loss at this step is equipment downtime (uptime 85%), about 139 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.