Brushed Stainless Elevator Cabin Wall Line

Product family: 304L Anti-Fingerprint Cab Panels.

Flow: Stainless steel mill → Coated Fiber Laser Cut → CNC Acoustic Core Slot → Dual-Servo Panel Bender → Acoustic Backing Foam Bond → Film Mask & Edge Guard Pack → Vertical Mobility OEMs

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Brushed Stainless Elevator Cabin Wall LineSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Stainless steel mill → Coated Fiber Laser Cut (306 s) → CNC Acoustic Core Slot (324 s) → Dual-Servo Panel Bender (486 s) → Acoustic Backing Foam Bond (378 s) → Film Mask & Edge Guard Pack (279 s) → Vertical Mobility OEMs.SUPPLIERStainless steelmillI1.80 d1Coated FiberLaser CutC/T 306 sI1.20 d2CNC Acoustic CoreSlotC/T 324 sI2.10 d3Dual-Servo PanelBenderC/T 486 sI1.70 d4Acoustic BackingFoam BondC/T 378 sI0.90 d5Film Mask & EdgeGuard PackC/T 279 sI1.20 dCUSTOMERVerticalMobility OEMs120 / parts

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Coated Fiber Laser Cut306 s20 min94%99.1%180216 (1.80 d)162
2. CNC Acoustic Core Slot324 s10 min95%98.4%60144 (1.20 d)152
3. Dual-Servo Panel Bender486 s55 min84%95.2%96252 (2.10 d)82
4. Acoustic Backing Foam Bond378 s35 min90%96.8%144204 (1.70 d)120
5. Film Mask & Edge Guard Pack279 s10 min96%99.0%36108 (0.90 d)177

Key figures

Takt time
450 s
Lead time
8.93 d
Value-added time
1,773 s
Process cycle efficiency (PCE)
0.37%
Rolled throughput yield (RTY)
89.0%
Customer demand per day
120 parts
Line capacity per day
82 parts
Bottleneck
Dual-Servo Panel Bender

Reading the bottleneck

The bottleneck is "Dual-Servo Panel Bender": it can process 82 parts per day against a demand of 120 parts, so it falls short of demand by 31.6%. Once downtime and scrap are counted, its cycle time grows from 486 s to 608 s, against a takt of 450 s. The largest loss at this step is equipment downtime (uptime 84%), about 92.6 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.