Sound-Attenuated Diesel Genset Canopy

Product family: Weatherproof 65dBA Enclosures.

Flow: Coated sheet mills → 12kW Fiber Laser Nest → CNC Louver Stamp & Bend → Robotic Roof Seam Seal → Zinc Primer & Polyester Coat → Stone-Wool Acoustic Line & Latch → Power Generation OEMs

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Sound-Attenuated Diesel Genset CanopySupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Coated sheet mills → 12kW Fiber Laser Nest (874 s) → CNC Louver Stamp & Bend (926 s) → Robotic Roof Seam Seal (1,389 s) → Zinc Primer & Polyester Coat (1,080 s) → Stone-Wool Acoustic Line & Latch (797 s) → Power Generation OEMs.SUPPLIERCoated sheetmillsI1.81 d112kW Fiber LaserNestC/T 874 sI1.19 d2CNC Louver Stamp& BendC/T 926 sI2.10 d3Robotic Roof SeamSealC/T 1,389 sI1.69 d4Zinc Primer &Polyester CoatC/T 1,080 sI0.90 d5Stone-WoolAcoustic Line &…C/T 797 sI1.19 dCUSTOMERPowerGeneration OEMs42 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. 12kW Fiber Laser Nest874 s20 min94%99.1%6376 (1.81 d)57
2. CNC Louver Stamp & Bend926 s10 min95%98.4%2150 (1.19 d)53
3. Robotic Roof Seam Seal1,389 s55 min84%95.2%3488 (2.10 d)29
4. Zinc Primer & Polyester Coat1,080 s35 min90%96.8%5071 (1.69 d)42
5. Stone-Wool Acoustic Line & Latch797 s10 min96%99.0%1338 (0.90 d)62

Key figures

Takt time
1,286 s
Lead time
8.97 d
Value-added time
5,066 s
Process cycle efficiency (PCE)
1.0%
Rolled throughput yield (RTY)
89.0%
Customer demand per day
42 units
Line capacity per day
29 units
Bottleneck
Robotic Roof Seam Seal

Reading the bottleneck

The bottleneck is "Robotic Roof Seam Seal": it can process 29 units per day against a demand of 42 units, so it falls short of demand by 31.6%. Once downtime and scrap are counted, its cycle time grows from 1,389 s to 1,737 s, against a takt of 1,286 s. The largest loss at this step is equipment downtime (uptime 84%), about 265 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.

Other scenarios in this family

More scenarios of Sheet Metal, Laser & Powder Coat: Sheet Metal, Laser & Powder Coat