UL-291 Bank ATM High-Security Safe Chest
Product family: CEN-IV Armored Cash Safes.
Flow: Wear-resistant & manganese plate → HD Plasma Armored Cut → Heavy Die Press Corner Bend → Multi-Pass Armored Flux Weld → Composite Cement Fill & Cure → Electronic Lock Bolt & Cert → Retail Banking Hardware
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. HD Plasma Armored Cut | 668 s | 20 min | 94% | 99.1% | 83 | 99 (1.80 d) | 74 |
| 2. Heavy Die Press Corner Bend | 707 s | 10 min | 95% | 98.4% | 28 | 66 (1.20 d) | 70 |
| 3. Multi-Pass Armored Flux Weld | 1,060 s | 55 min | 84% | 95.2% | 44 | 116 (2.11 d) | 38 |
| 4. Composite Cement Fill & Cure | 825 s | 35 min | 90% | 96.8% | 66 | 94 (1.71 d) | 55 |
| 5. Electronic Lock Bolt & Cert | 609 s | 10 min | 96% | 99.0% | 17 | 50 (0.91 d) | 81 |
Key figures
- Takt time
- 982 s
- Lead time
- 9.00 d
- Value-added time
- 3,869 s
- Process cycle efficiency (PCE)
- 0.80%
- Rolled throughput yield (RTY)
- 89.0%
- Customer demand per day
- 55 units
- Line capacity per day
- 38 units
- Bottleneck
- Multi-Pass Armored Flux Weld
Reading the bottleneck
The bottleneck is "Multi-Pass Armored Flux Weld": it can process 38 units per day against a demand of 55 units, so it falls short of demand by 31.6%. Once downtime and scrap are counted, its cycle time grows from 1,060 s to 1,326 s, against a takt of 982 s. The largest loss at this step is equipment downtime (uptime 84%), about 202 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Sheet Metal, Laser & Powder Coat: Sheet Metal, Laser & Powder Coat
- Sheet Metal Laser, Bending & Powder Coat
- 42U Hyperscale Data Center Rack Enclosure
- Brushed Stainless Elevator Cabin Wall Line
- Galvanized Spiral & Rectangular HVAC Duct Line
- Torque-Tube Roll-Formed Solar Tracker Beam
- Sanitary Welded 316L Stainless Feed Hopper
- Sound-Attenuated Diesel Genset Canopy
- Modular Stainless Intralogistics Conveyor
- Commercial UL Grease-Filter Exhaust Hood
- Telescopic Hexagonal Mobile Crane Boom
- Flush Pharma Cleanroom Airlock Partition