Torque-Tube Roll-Formed Solar Tracker Beam

Product family: Octagonal Galvanized Tracker Beams.

Flow: Strip steel supplier → High-Speed Coil Slitting → 16-Pass Octagonal Roll Mill → Flying Laser Hole Pierce → Flange Plate Mag-Weld → Bundle Strapping 40-Pack → Utility Solar EPC Sites

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Torque-Tube Roll-Formed Solar Tracker BeamSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Strip steel supplier → High-Speed Coil Slitting (59.0 s) → 16-Pass Octagonal Roll Mill (63.0 s) → Flying Laser Hole Pierce (94.0 s) → Flange Plate Mag-Weld (73.0 s) → Bundle Strapping 40-Pack (54.0 s) → Utility Solar EPC Sites.SUPPLIERStrip steelsupplierI1.80 d1High-Speed CoilSlittingC/T 59.0 sI1.20 d216-Pass OctagonalRoll MillC/T 63.0 sI2.10 d3Flying Laser HolePierceC/T 94.0 sI1.70 d4Flange PlateMag-WeldC/T 73.0 sI0.90 d5Bundle Strapping40-PackC/T 54.0 sI1.20 dCUSTOMERUtility SolarEPC Sites620 / parts

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. High-Speed Coil Slitting59.0 s20 min94%99.1%9301,116 (1.80 d)840
2. 16-Pass Octagonal Roll Mill63.0 s10 min95%98.4%310744 (1.20 d)783
3. Flying Laser Hole Pierce94.0 s55 min84%95.2%4961,302 (2.10 d)424
4. Flange Plate Mag-Weld73.0 s35 min90%96.8%7441,054 (1.70 d)624
5. Bundle Strapping 40-Pack54.0 s10 min96%99.0%186558 (0.90 d)915

Key figures

Takt time
87.1 s
Lead time
8.91 d
Value-added time
343 s
Process cycle efficiency (PCE)
0.071%
Rolled throughput yield (RTY)
89.0%
Customer demand per day
620 parts
Line capacity per day
424 parts
Bottleneck
Flying Laser Hole Pierce

Reading the bottleneck

The bottleneck is "Flying Laser Hole Pierce": it can process 424 parts per day against a demand of 620 parts, so it falls short of demand by 31.6%. Once downtime and scrap are counted, its cycle time grows from 94.0 s to 118 s, against a takt of 87.1 s. The largest loss at this step is equipment downtime (uptime 84%), about 17.9 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.