Commercial UL Grease-Filter Exhaust Hood
Product family: Stainless Restaurant Canopies.
Flow: Brushed 304SS Mills → CNC Shear & Corner Notch → TIG Liquid-Tight Seam Weld → Grind & #4 Satin Polish → Baffle & Fire Nozzle Plumb → White-Glove Crate Wrapping → Commercial Kitchen Builders
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. CNC Shear & Corner Notch | 525 s | 20 min | 94% | 99.1% | 53 | 63 (1.80 d) | 47 |
| 2. TIG Liquid-Tight Seam Weld | 555 s | 10 min | 95% | 98.4% | 18 | 42 (1.20 d) | 44 |
| 3. Grind & #4 Satin Polish | 833 s | 55 min | 84% | 95.2% | 28 | 74 (2.11 d) | 22 |
| 4. Baffle & Fire Nozzle Plumb | 648 s | 35 min | 90% | 96.8% | 42 | 60 (1.71 d) | 34 |
| 5. White-Glove Crate Wrapping | 478 s | 10 min | 96% | 99.0% | 11 | 32 (0.91 d) | 50 |
Key figures
- Takt time
- 771 s
- Lead time
- 9.06 d
- Value-added time
- 3,039 s
- Process cycle efficiency (PCE)
- 1.2%
- Rolled throughput yield (RTY)
- 89.0%
- Customer demand per day
- 35 units
- Line capacity per day
- 22 units
- Bottleneck
- Grind & #4 Satin Polish
Reading the bottleneck
The bottleneck is "Grind & #4 Satin Polish": it can process 22 units per day against a demand of 35 units, so it falls short of demand by 37.3%. Once downtime and scrap are counted, its cycle time grows from 833 s to 1,042 s, against a takt of 771 s. The largest loss at this step is equipment downtime (uptime 84%), about 159 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Sheet Metal, Laser & Powder Coat: Sheet Metal, Laser & Powder Coat
- Sheet Metal Laser, Bending & Powder Coat
- 42U Hyperscale Data Center Rack Enclosure
- Brushed Stainless Elevator Cabin Wall Line
- Galvanized Spiral & Rectangular HVAC Duct Line
- Torque-Tube Roll-Formed Solar Tracker Beam
- Sanitary Welded 316L Stainless Feed Hopper
- Sound-Attenuated Diesel Genset Canopy
- UL-291 Bank ATM High-Security Safe Chest
- Modular Stainless Intralogistics Conveyor
- Telescopic Hexagonal Mobile Crane Boom
- Flush Pharma Cleanroom Airlock Partition