Articulating Powered Endoscopic Linear Stapler

Product family: Single-Use 60mm Endo-Reloads.

Flow: 304SS Micro-Wire & PEEK → Micro-Wire Titanium Form → Cleanroom Staple Cart Load → Surgical Steel Blade Laser Weld → Trigger Firing Force Test → Blister Seal & Gamma Cycle → Laparoscopic Surgical Suites

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Articulating Powered Endoscopic Linear StaplerSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. 304SS Micro-Wire & PEEK → Micro-Wire Titanium Form (19.9 s) → Cleanroom Staple Cart Load (22.2 s) → Surgical Steel Blade Laser Weld (30.7 s) → Trigger Firing Force Test (20.5 s) → Blister Seal & Gamma Cycle (23.3 s) → Laparoscopic Surgical Suites.SUPPLIER304SSMicro-Wire &PEEKI1.70 d1Micro-WireTitanium FormC/T 19.9 sI1.50 d2Cleanroom StapleCart LoadC/T 22.2 sI1.90 d3Surgical SteelBlade Laser WeldC/T 30.7 sI1.00 d4Trigger FiringForce TestC/T 20.5 sI2.40 d5Blister Seal &Gamma CycleC/T 23.3 sI2.00 dCUSTOMERLaparoscopicSurgical Suites1,900 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Micro-Wire Titanium Form19.9 s30 min94%98.5%1,9003,230 (1.70 d)2,429
2. Cleanroom Staple Cart Load22.2 s25 min92%97.8%1,5202,850 (1.50 d)2,113
3. Surgical Steel Blade Laser Weld30.7 s20 min86%94.8%9503,610 (1.90 d)1,370
4. Trigger Firing Force Test20.5 s12 min95%98.9%7601,900 (1.00 d)2,392
5. Blister Seal & Gamma Cycle23.3 s15 min92%98.4%2,8504,560 (2.40 d)2,075

Key figures

Takt time
28.4 s
Lead time
10.5 d
Value-added time
117 s
Process cycle efficiency (PCE)
0.021%
Rolled throughput yield (RTY)
88.9%
Customer demand per day
1,900 units
Line capacity per day
1,370 units
Bottleneck
Surgical Steel Blade Laser Weld

Reading the bottleneck

The bottleneck is "Surgical Steel Blade Laser Weld": it can process 1,370 units per day against a demand of 1,900 units, so it falls short of demand by 27.9%. Once downtime and scrap are counted, its cycle time grows from 30.7 s to 37.7 s, against a takt of 28.4 s. The largest loss at this step is equipment downtime (uptime 86%), about 5.0 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.