Hermetic MRI-Safe Cardiac Pacemaker Can
Product family: 12-Year Li-CFx Titanium Can.
Flow: Medical Battery & Titanium Suppliers → Micro-Hybrid Board Reflow → Li-CFx Cell & Ti Case Insert → Nd:YAG Laser Hermetic Seam → Helium Mass-Spec 1e-9 Leak → Thermal Soak & Programmer Check → Cardiac Electrophysiology
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Micro-Hybrid Board Reflow | 90.0 s | 30 min | 94% | 98.5% | 420 | 714 (1.70 d) | 537 |
| 2. Li-CFx Cell & Ti Case Insert | 100 s | 25 min | 92% | 97.8% | 336 | 630 (1.50 d) | 469 |
| 3. Nd:YAG Laser Hermetic Seam | 139 s | 20 min | 86% | 94.8% | 210 | 798 (1.90 d) | 303 |
| 4. Helium Mass-Spec 1e-9 Leak | 93.0 s | 12 min | 95% | 98.9% | 168 | 420 (1.00 d) | 527 |
| 5. Thermal Soak & Programmer Check | 105 s | 15 min | 92% | 98.4% | 630 | 1,008 (2.40 d) | 460 |
Key figures
- Takt time
- 129 s
- Lead time
- 10.5 d
- Value-added time
- 527 s
- Process cycle efficiency (PCE)
- 0.093%
- Rolled throughput yield (RTY)
- 88.9%
- Customer demand per day
- 420 units
- Line capacity per day
- 303 units
- Bottleneck
- Nd:YAG Laser Hermetic Seam
Reading the bottleneck
The bottleneck is "Nd:YAG Laser Hermetic Seam": it can process 303 units per day against a demand of 420 units, so it falls short of demand by 27.9%. Once downtime and scrap are counted, its cycle time grows from 139 s to 170 s, against a takt of 129 s. The largest loss at this step is equipment downtime (uptime 86%), about 22.6 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Implantable & Surgical MedTech: Implantable & Surgical MedTech
- CoCr Laser-Cut Drug-Eluting Coronary Stent
- Porous 3D-Printed Titanium Hip Acetabular Cup
- High-Flux Polysulfone Hollow-Fiber Dialyzer
- Articulating Powered Endoscopic Linear Stapler
- Tubeless Wearable Micro-Fluidic Patch Pump
- Hydrophobic Acrylic Foldable Cataract IOL
- 16-Channel Flexible 3T MRI RF Receiver Coil
- Rechargeable RIC Digital Hearing Aid Micro-Shell
- Reusable Silicone Pediatric SpO2 Finger Sensor
- Closed-System Vacuum PMMA Bone Cement Mixer
- Steerable Braided 8F Electrophysiology Catheter