High-Flux Polysulfone Hollow-Fiber Dialyzer

Product family: Single-Use Hemodialysis Carts.

Flow: Polysulfone Resin Supplier → Poly-Membrane Wet-Spin Bundle → Fiber Bundle Insert & Cut → Centrifugal Polyurethane Pot → Header Cap Ultrasonic Weld → 100% Bubble-Point & EtO/Steam → Dialysis Clinic Chains

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: High-Flux Polysulfone Hollow-Fiber DialyzerSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Polysulfone Resin Supplier → Poly-Membrane Wet-Spin Bundle (8.3 s) → Fiber Bundle Insert & Cut (9.3 s) → Centrifugal Polyurethane Pot (12.9 s) → Header Cap Ultrasonic Weld (8.6 s) → 100% Bubble-Point & EtO/Steam (9.8 s) → Dialysis Clinic Chains.SUPPLIERPolysulfoneResin SupplierI1.70 d1Poly-MembraneWet-Spin BundleC/T 8.3 sI1.50 d2Fiber BundleInsert & CutC/T 9.3 sI1.90 d3CentrifugalPolyurethane PotC/T 12.9 sI1.00 d4Header CapUltrasonic WeldC/T 8.6 sI2.40 d5100% Bubble-Point& EtO/SteamC/T 9.8 sI2.00 dCUSTOMERDialysis ClinicChains6,800 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Poly-Membrane Wet-Spin Bundle8.3 s30 min94%98.5%6,80011,560 (1.70 d)8,835
2. Fiber Bundle Insert & Cut9.3 s25 min92%97.8%5,44010,200 (1.50 d)7,655
3. Centrifugal Polyurethane Pot12.9 s20 min86%94.8%3,40012,920 (1.90 d)4,968
4. Header Cap Ultrasonic Weld8.6 s12 min95%98.9%2,7206,800 (1.00 d)8,653
5. 100% Bubble-Point & EtO/Steam9.8 s15 min92%98.4%10,20016,320 (2.40 d)7,427

Key figures

Takt time
11.9 s
Lead time
10.5 d
Value-added time
48.9 s
Process cycle efficiency (PCE)
0.006%
Rolled throughput yield (RTY)
88.9%
Customer demand per day
6,800 units
Line capacity per day
4,968 units
Bottleneck
Centrifugal Polyurethane Pot

Reading the bottleneck

The bottleneck is "Centrifugal Polyurethane Pot": it can process 4,968 units per day against a demand of 6,800 units, so it falls short of demand by 26.9%. Once downtime and scrap are counted, its cycle time grows from 12.9 s to 15.8 s, against a takt of 11.9 s. The largest loss at this step is equipment downtime (uptime 86%), about 2.1 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.