Pre-Mixed Sterile Pain Management Mini-Bag
Product family: OR Epidural Infusion Packs.
Flow: Medical-Grade EVA Film Supplier → Bulk Analgesic Dissolution → Aseptic EVA Port Filling → Terminal Steam Air-Overpress → Secondary UV Shield Overwrap → QA Micro & Release Pack → Surgical Anesthesia Suites
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Bulk Analgesic Dissolution | 5.9 s | 45 min | 95% | 99.4% | 6,200 | 8,680 (1.40 d) | 8,211 |
| 2. Aseptic EVA Port Filling | 9.4 s | 95 min | 82% | 95.8% | 6,200 | 13,640 (2.20 d) | 4,036 |
| 3. Terminal Steam Air-Overpress | 6.8 s | 25 min | 92% | 96.8% | 3,100 | 8,060 (1.30 d) | 6,679 |
| 4. Secondary UV Shield Overwrap | 5.6 s | 20 min | 95% | 99.1% | 2,480 | 6,200 (1.00 d) | 8,574 |
| 5. QA Micro & Release Pack | 7.0 s | 10 min | 93% | 98.5% | 6,200 | 14,880 (2.40 d) | 6,988 |
Key figures
- Takt time
- 8.7 s
- Lead time
- 9.80 d
- Value-added time
- 34.7 s
- Process cycle efficiency (PCE)
- 0.007%
- Rolled throughput yield (RTY)
- 90.0%
- Customer demand per day
- 6,200 packs
- Line capacity per day
- 4,036 packs
- Bottleneck
- Aseptic EVA Port Filling
Reading the bottleneck
The bottleneck is "Aseptic EVA Port Filling": it can process 4,036 packs per day against a demand of 6,200 packs, so it falls short of demand by 34.9%. Once downtime and scrap are counted, its cycle time grows from 9.4 s to 12.0 s, against a takt of 8.7 s. The largest loss at this step is equipment downtime (uptime 82%), about 2.1 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Sterile Injectable & Aseptic GMP: Sterile Injectable & Aseptic GMP
- Sterile Vial Fill-Finish & QC Release
- RTU Pre-Filled Glass Syringe Aseptic Line
- Oncology Cytotoxic Lyophilized Powder Vial
- Preservative-Free Ophthalmic Eye Dropper
- 1000mL PP Intravenous IV Infusion Bag Line
- 3mL Glass Cartridge & Disposable Insulin Pen
- Blow-Fill-Seal (BFS) Single-Dose Inhalation Ampoule
- mRNA Lipid Nanoparticle (LNP) Ultra-Cold Vial
- 2mL OPC Glass Ampoule Flame-Seal Line
- Sterile Anticoagulant Heparin Multi-Dose Vial
- CT/MRI Gadolinium Contrast Polymer Bottle