1000mL PP Intravenous IV Infusion Bag Line
Product family: High-Volume Normal Saline.
Flow: Polypropylene Film Supplier → Tube Extrusion & Port Weld → WFI Water & NaCl Dissolve → Rotary 12-Head Fill & Overpouch → Superheated Water Autoclave → 100% Overpouch Leak & Case → Public Hospital Tenders
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Tube Extrusion & Port Weld | 2.0 s | 45 min | 95% | 99.4% | 28,000 | 39,200 (1.40 d) | 36,969 |
| 2. WFI Water & NaCl Dissolve | 3.1 s | 95 min | 82% | 95.8% | 28,000 | 61,600 (2.20 d) | 19,082 |
| 3. Rotary 12-Head Fill & Overpouch | 2.3 s | 25 min | 92% | 96.8% | 14,000 | 36,400 (1.30 d) | 30,202 |
| 4. Superheated Water Autoclave | 1.9 s | 20 min | 95% | 99.1% | 11,200 | 28,000 (1.00 d) | 38,649 |
| 5. 100% Overpouch Leak & Case | 2.3 s | 10 min | 93% | 98.5% | 28,000 | 67,200 (2.40 d) | 32,022 |
Key figures
- Takt time
- 2.9 s
- Lead time
- 9.80 d
- Value-added time
- 11.6 s
- Process cycle efficiency (PCE)
- 0.001%
- Rolled throughput yield (RTY)
- 90.0%
- Customer demand per day
- 28,000 packs
- Line capacity per day
- 19,082 packs
- Bottleneck
- WFI Water & NaCl Dissolve
Reading the bottleneck
The bottleneck is "WFI Water & NaCl Dissolve": it can process 19,082 packs per day against a demand of 28,000 packs, so it falls short of demand by 31.9%. Once downtime and scrap are counted, its cycle time grows from 3.1 s to 3.9 s, against a takt of 2.9 s. The largest loss at this step is equipment downtime (uptime 82%), about 0.7 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Sterile Injectable & Aseptic GMP: Sterile Injectable & Aseptic GMP
- Sterile Vial Fill-Finish & QC Release
- RTU Pre-Filled Glass Syringe Aseptic Line
- Oncology Cytotoxic Lyophilized Powder Vial
- Preservative-Free Ophthalmic Eye Dropper
- 3mL Glass Cartridge & Disposable Insulin Pen
- Blow-Fill-Seal (BFS) Single-Dose Inhalation Ampoule
- mRNA Lipid Nanoparticle (LNP) Ultra-Cold Vial
- 2mL OPC Glass Ampoule Flame-Seal Line
- Sterile Anticoagulant Heparin Multi-Dose Vial
- CT/MRI Gadolinium Contrast Polymer Bottle
- Pre-Mixed Sterile Pain Management Mini-Bag