CT/MRI Gadolinium Contrast Polymer Bottle

Product family: Radiology Contrast Injectables.

Flow: Contrast Agent API Suppliers → Chelate Complex Blending → Blow-Mold Medical Resin → Barrier Isolator Sterile Fill → Moist-Heat Terminal Cycle → Batch Potency & Cartoning → Radiology Imaging Centers

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: CT/MRI Gadolinium Contrast Polymer BottleSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Contrast Agent API Suppliers → Chelate Complex Blending (3.9 s) → Blow-Mold Medical Resin (6.1 s) → Barrier Isolator Sterile Fill (4.4 s) → Moist-Heat Terminal Cycle (3.6 s) → Batch Potency & Cartoning (4.5 s) → Radiology Imaging Centers.SUPPLIERContrast AgentAPI SuppliersI1.40 d1Chelate ComplexBlendingC/T 3.9 sI2.20 d2Blow-Mold MedicalResinC/T 6.1 sI1.30 d3Barrier IsolatorSterile FillC/T 4.4 sI1.00 d4Moist-HeatTerminal CycleC/T 3.6 sI2.40 d5Batch Potency &CartoningC/T 4.5 sI1.50 dCUSTOMERRadiologyImaging Centers9,500 / vials

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Chelate Complex Blending3.9 s45 min95%99.4%9,50013,300 (1.40 d)12,421
2. Blow-Mold Medical Resin6.1 s95 min82%95.8%9,50020,900 (2.20 d)6,220
3. Barrier Isolator Sterile Fill4.4 s25 min92%96.8%4,75012,350 (1.30 d)10,322
4. Moist-Heat Terminal Cycle3.6 s20 min95%99.1%3,8009,500 (1.00 d)13,337
5. Batch Potency & Cartoning4.5 s10 min93%98.5%9,50022,800 (2.40 d)10,870

Key figures

Takt time
5.7 s
Lead time
9.80 d
Value-added time
22.5 s
Process cycle efficiency (PCE)
0.004%
Rolled throughput yield (RTY)
90.0%
Customer demand per day
9,500 vials
Line capacity per day
6,220 vials
Bottleneck
Blow-Mold Medical Resin

Reading the bottleneck

The bottleneck is "Blow-Mold Medical Resin": it can process 6,220 vials per day against a demand of 9,500 vials, so it falls short of demand by 34.5%. Once downtime and scrap are counted, its cycle time grows from 6.1 s to 7.8 s, against a takt of 5.7 s. The largest loss at this step is equipment downtime (uptime 82%), about 1.3 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.