Acoustic Anechoic Smart Speaker / Mic Array Tune

Product family: Beamforming Audio Tuning.

Flow: Acoustic HATS Head & Torso → HATS Head Calibration Mount → 360° Polar Frequency Sweep → Far-Field Wakeword Noise Mix → Biquad & AEC DSP Filter Tune → Golden Reference Curve Lock → Consumer Audio Product

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Acoustic Anechoic Smart Speaker / Mic Array TuneSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Acoustic HATS Head & Torso → HATS Head Calibration Mount (1,389 s) → 360° Polar Frequency Sweep (1,620 s) → Far-Field Wakeword Noise Mix (2,083 s) → Biquad & AEC DSP Filter Tune (1,466 s) → Golden Reference Curve Lock (1,080 s) → Consumer Audio Product.SUPPLIERAcoustic HATSHead & TorsoI2.00 d1HATS HeadCalibration MountC/T 1,389 sI1.79 d2360° PolarFrequency SweepC/T 1,620 sI3.00 d3Far-FieldWakeword Noise…C/T 2,083 sI1.21 d4Biquad & AEC DSPFilter TuneC/T 1,466 sI0.71 d5Golden ReferenceCurve LockC/T 1,080 sI1.00 dCUSTOMERConsumer AudioProduct14 / cases

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. HATS Head Calibration Mount1,389 s20 min94%96.5%1128 (2.00 d)17
2. 360° Polar Frequency Sweep1,620 s15 min91%93.8%725 (1.79 d)13
3. Far-Field Wakeword Noise Mix2,083 s35 min83%89.5%1142 (3.00 d)9
4. Biquad & AEC DSP Filter Tune1,466 s12 min94%97.6%617 (1.21 d)16
5. Golden Reference Curve Lock1,080 s5 min98%99.1%310 (0.71 d)23

Key figures

Takt time
1,929 s
Lead time
10.00 d
Value-added time
7,638 s
Process cycle efficiency (PCE)
2.8%
Rolled throughput yield (RTY)
78.4%
Customer demand per day
14 cases
Line capacity per day
9 cases
Bottleneck
Far-Field Wakeword Noise Mix

Reading the bottleneck

The bottleneck is "Far-Field Wakeword Noise Mix": it can process 9 cases per day against a demand of 14 cases, so it falls short of demand by 38.0%. Once downtime and scrap are counted, its cycle time grows from 2,083 s to 2,804 s, against a takt of 1,929 s. The largest loss at this step is equipment downtime (uptime 83%), about 427 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.