Colocation Data Center Fiber Cross-Connect SLA

Product family: 24-Hr Carrier Cage Patching.

Flow: Carrier Meet-Me-Room → Customer LOA CFA Validation → Pathway Tray Routing Audit → Meet-Me-Room Patch & Clean → Bi-Dir Light Meter Loss QC → BGP Link Up Completion Email → Cloud & Fintech Tenants

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Colocation Data Center Fiber Cross-Connect SLASupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Carrier Meet-Me-Room → Customer LOA CFA Validation (540 s) → Pathway Tray Routing Audit (619 s) → Meet-Me-Room Patch & Clean (858 s) → Bi-Dir Light Meter Loss QC (572 s) → BGP Link Up Completion Email (357 s) → Cloud & Fintech Tenants.SUPPLIERCarrierMeet-Me-RoomI2.00 d1Customer LOA CFAValidationC/T 540 sI1.79 d2Pathway TrayRouting AuditC/T 619 sI2.60 d3Meet-Me-RoomPatch & CleanC/T 858 sI0.79 d4Bi-Dir LightMeter Loss QCC/T 572 sI0.40 d5BGP Link UpCompletion EmailC/T 357 sI0.50 dCUSTOMERCloud & FintechTenants68 / lines

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Customer LOA CFA Validation540 s5 min95%93.0%20136 (2.00 d)87
2. Pathway Tray Routing Audit619 s15 min92%95.8%27122 (1.79 d)74
3. Meet-Me-Room Patch & Clean858 s20 min84%91.0%20177 (2.60 d)44
4. Bi-Dir Light Meter Loss QC572 s5 min95%96.8%1054 (0.79 d)84
5. BGP Link Up Completion Email357 s2 min99%99.1%727 (0.40 d)145

Key figures

Takt time
794 s
Lead time
8.14 d
Value-added time
2,946 s
Process cycle efficiency (PCE)
0.67%
Rolled throughput yield (RTY)
77.8%
Customer demand per day
68 lines
Line capacity per day
44 lines
Bottleneck
Meet-Me-Room Patch & Clean

Reading the bottleneck

The bottleneck is "Meet-Me-Room Patch & Clean": it can process 44 lines per day against a demand of 68 lines, so it falls short of demand by 34.6%. Once downtime and scrap are counted, its cycle time grows from 858 s to 1,122 s, against a takt of 794 s. The largest loss at this step is equipment downtime (uptime 84%), about 163 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.