FTTH Fiber Drop & Service Activation
Product family: FTTH B2C & B2B Fiber Links.
Flow: Fiber Optic & Civil Ops → Permit & Splitter Port → Civil Conduit Check → Field Drop & Splicing → OTDR & ONT Provision → Billing Live Activation → Broadband Subscribers
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Permit & Splitter Port | 204 s | 5 min | 95% | 93.0% | 27 | 180 (2.00 d) | 113 |
| 2. Civil Conduit Check | 234 s | 15 min | 92% | 95.8% | 36 | 162 (1.80 d) | 93 |
| 3. Field Drop & Splicing | 324 s | 20 min | 84% | 91.0% | 27 | 234 (2.60 d) | 54 |
| 4. OTDR & ONT Provision | 216 s | 5 min | 95% | 96.8% | 14 | 72 (0.80 d) | 107 |
| 5. Billing Live Activation | 135 s | 2 min | 99% | 99.1% | 9 | 36 (0.40 d) | 187 |
Key figures
- Takt time
- 300 s
- Lead time
- 8.14 d
- Value-added time
- 1,113 s
- Process cycle efficiency (PCE)
- 0.51%
- Rolled throughput yield (RTY)
- 77.8%
- Customer demand per day
- 90 lines
- Line capacity per day
- 54 lines
- Bottleneck
- Field Drop & Splicing
Reading the bottleneck
The bottleneck is "Field Drop & Splicing": it can process 54 lines per day against a demand of 90 lines, so it falls short of demand by 39.7%. Once downtime and scrap are counted, its cycle time grows from 324 s to 424 s, against a takt of 300 s. The largest loss at this step is equipment downtime (uptime 84%), about 61.7 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Telecom Networks, Fiber FTTH & 5G: Telecom Networks, Fiber FTTH & 5G
- 5G Standalone (SA) Urban Macro Site Upgrade
- Global Enterprise SD-WAN Retail Branch Cutover
- Colocation Data Center Fiber Cross-Connect SLA
- B2B Fleet IoT Global eSIM M2M Activation Flow
- Enterprise SIP Trunk & Regulatory Number Port
- Metro Dark Fiber Ring Lease & Splicing Turn-Up
- Licensed E-Band 10Gbps Microwave Backhaul Link
- Rural 5G Fixed-Wireless (FWA) Outdoor CPE Setup
- Tier-1 Backbone Router 400G Linecard Upgrade
- MVNO Wholesale CDR Mediation & Invoice Cycle
- Subsea Repeatered Cable Ship Shunt Fault Fix