Double-Wall Aqueous-Coated Disposable Paper Cup
Product family: Plastic-Free Barrier Cold/Hot.
Flow: Cup Paperboard Producer → Food-Safe Flexo Web Printing → Flatbed Fan Blank Die-Cutting → 160-cpm Ultrasonic Side/Bot → Outer Embossed Sleeve Bond → Rim Leak Test & Auto Bagging → Coffee Chains & Stadiums
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Food-Safe Flexo Web Printing | 1.2 s | 25 min | 94% | 98.8% | 140,000 | 182,000 (1.30 d) | 61,528 |
| 2. Flatbed Fan Blank Die-Cutting | 1.2 s | 40 min | 91% | 97.6% | 112,000 | 210,000 (1.50 d) | 57,730 |
| 3. 160-cpm Ultrasonic Side/Bot | 1.2 s | 45 min | 84% | 95.8% | 112,000 | 252,000 (1.80 d) | 52,055 |
| 4. Outer Embossed Sleeve Bond | 1.2 s | 5 min | 97% | 98.9% | 35,000 | 98,000 (0.70 d) | 63,795 |
| 5. Rim Leak Test & Auto Bagging | 1.2 s | 8 min | 97% | 99.5% | 42,000 | 112,000 (0.80 d) | 63,861 |
Key figures
- Takt time
- 0.6 s
- Lead time
- 7.60 d
- Value-added time
- 6.0 s
- Process cycle efficiency (PCE)
- 0.001%
- Rolled throughput yield (RTY)
- 90.9%
- Customer demand per day
- 140,000 units
- Line capacity per day
- 52,055 units
- Bottleneck
- 160-cpm Ultrasonic Side/Bot
Reading the bottleneck
The bottleneck is "160-cpm Ultrasonic Side/Bot": it can process 52,055 units per day against a demand of 140,000 units, so it falls short of demand by 62.8%. Once downtime and scrap are counted, its cycle time grows from 1.2 s to 1.5 s, against a takt of 0.6 s. The largest loss at this step is equipment downtime (uptime 84%), about 0.2 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Pulp, Paper Mills & Corrugated Boxes: Pulp, Paper Mills & Corrugated Boxes
- High-Speed Corrugated E-Commerce Box Line
- 900-Ton/Day Recycled Testliner Packaging Mill
- 3-Ply Virgin/Bamboo Toilet & Towel Converting
- 6-Pack Wet-Strength Beer Basket Carrier Carton
- 100% Bagasse Molded Pulp Food Clamshell Line
- Ultra-Thin 45gsm Miniature Pharma Outsert Line
- BPA-Free Thermal POS Receipt & Scale Roll Line
- Watermark Cotton Paper & Hologram Security Sheet
- High-Humidity Wax-Free Export Citrus Box
- Custom Multi-Tier Printed Retail Floor Display
- Reinforced Fiberglass Water-Activated Gummed Tape