Reinforced Fiberglass Water-Activated Gummed Tape

Product family: Tamper-Evident Carton Seal Rolls.

Flow: Unbleached 70gsm Kraft → Cross-Weave Fiberglass Laminate → Rotary Potato-Starch Gum Coat → Multi-Pass Tunnel Steam Dry → Precision Shear Slit to 72mm → Moisture-Seal Poly Carton → E-Commerce Fulfillment Centers

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Reinforced Fiberglass Water-Activated Gummed TapeSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Unbleached 70gsm Kraft → Cross-Weave Fiberglass Laminate (1.6 s) → Rotary Potato-Starch Gum Coat (1.8 s) → Multi-Pass Tunnel Steam Dry (2.4 s) → Precision Shear Slit to 72mm (1.5 s) → Moisture-Seal Poly Carton (1.3 s) → E-Commerce Fulfillment Centers.SUPPLIERUnbleached70gsm KraftI1.30 d1Cross-WeaveFiberglass…C/T 1.6 sI1.50 d2RotaryPotato-Starch Gu…C/T 1.8 sI1.80 d3Multi-Pass TunnelSteam DryC/T 2.4 sI0.70 d4Precision ShearSlit to 72mmC/T 1.5 sI0.80 d5Moisture-SealPoly CartonC/T 1.3 sI1.50 dCUSTOMERE-CommerceFulfillment…24,000 / packs

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Cross-Weave Fiberglass Laminate1.6 s25 min94%98.8%24,00031,200 (1.30 d)30,474
2. Rotary Potato-Starch Gum Coat1.8 s40 min91%97.6%19,20036,000 (1.50 d)25,165
3. Multi-Pass Tunnel Steam Dry2.4 s45 min84%95.8%19,20043,200 (1.80 d)16,975
4. Precision Shear Slit to 72mm1.5 s5 min97%98.9%6,00016,800 (0.70 d)33,768
5. Moisture-Seal Poly Carton1.3 s8 min97%99.5%7,20019,200 (0.80 d)38,903

Key figures

Takt time
2.3 s
Lead time
7.60 d
Value-added time
8.6 s
Process cycle efficiency (PCE)
0.002%
Rolled throughput yield (RTY)
90.9%
Customer demand per day
24,000 packs
Line capacity per day
16,975 packs
Bottleneck
Multi-Pass Tunnel Steam Dry

Reading the bottleneck

The bottleneck is "Multi-Pass Tunnel Steam Dry": it can process 16,975 packs per day against a demand of 24,000 packs, so it falls short of demand by 29.3%. Once downtime and scrap are counted, its cycle time grows from 2.4 s to 3.0 s, against a takt of 2.3 s. The largest loss at this step is equipment downtime (uptime 84%), about 0.5 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.