Watermark Cotton Paper & Hologram Security Sheet
Product family: Banknote & Passport Substrates.
Flow: Cotton Linters & UV Fibers → Cylinder Mould 3D Watermark → Windowed Security Thread Weave → Gelatin Surface Size & Calender → Automatic Sheet Defect Vision → Ream Vault Count & Security → National Central Banks
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Cylinder Mould 3D Watermark | 1.3 s | 25 min | 94% | 98.8% | 28,000 | 36,400 (1.30 d) | 37,506 |
| 2. Windowed Security Thread Weave | 1.6 s | 40 min | 91% | 97.6% | 22,400 | 42,000 (1.50 d) | 28,310 |
| 3. Gelatin Surface Size & Calender | 2.1 s | 45 min | 84% | 95.8% | 22,400 | 50,400 (1.80 d) | 19,400 |
| 4. Automatic Sheet Defect Vision | 1.3 s | 5 min | 97% | 98.9% | 7,000 | 19,600 (0.70 d) | 38,964 |
| 5. Ream Vault Count & Security | 1.2 s | 8 min | 97% | 99.5% | 8,400 | 22,400 (0.80 d) | 42,145 |
Key figures
- Takt time
- 1.9 s
- Lead time
- 7.60 d
- Value-added time
- 7.5 s
- Process cycle efficiency (PCE)
- 0.002%
- Rolled throughput yield (RTY)
- 90.9%
- Customer demand per day
- 28,000 parts
- Line capacity per day
- 19,400 parts
- Bottleneck
- Gelatin Surface Size & Calender
Reading the bottleneck
The bottleneck is "Gelatin Surface Size & Calender": it can process 19,400 parts per day against a demand of 28,000 parts, so it falls short of demand by 30.7%. Once downtime and scrap are counted, its cycle time grows from 2.1 s to 2.6 s, against a takt of 1.9 s. The largest loss at this step is equipment downtime (uptime 84%), about 0.4 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Pulp, Paper Mills & Corrugated Boxes: Pulp, Paper Mills & Corrugated Boxes
- High-Speed Corrugated E-Commerce Box Line
- 900-Ton/Day Recycled Testliner Packaging Mill
- 3-Ply Virgin/Bamboo Toilet & Towel Converting
- 6-Pack Wet-Strength Beer Basket Carrier Carton
- 100% Bagasse Molded Pulp Food Clamshell Line
- Ultra-Thin 45gsm Miniature Pharma Outsert Line
- Double-Wall Aqueous-Coated Disposable Paper Cup
- BPA-Free Thermal POS Receipt & Scale Roll Line
- High-Humidity Wax-Free Export Citrus Box
- Custom Multi-Tier Printed Retail Floor Display
- Reinforced Fiberglass Water-Activated Gummed Tape