100% Bagasse Molded Pulp Food Clamshell Line

Product family: PFAS-Free Compostable Trays.

Flow: Sugarcane Bagasse & Bamboo → Refiner Hydropulp & AKD Sizing → Thermoform Rotary Vacuum Mold → Hot-Press In-Mold Smooth Dry → Laser Trim & Stack Count → Clean Poly Sleeve & Pallet → QSR Foodservice Chains

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: 100% Bagasse Molded Pulp Food Clamshell LineSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Sugarcane Bagasse & Bamboo → Refiner Hydropulp & AKD Sizing (1.2 s) → Thermoform Rotary Vacuum Mold (1.2 s) → Hot-Press In-Mold Smooth Dry (1.2 s) → Laser Trim & Stack Count (1.2 s) → Clean Poly Sleeve & Pallet (1.2 s) → QSR Foodservice Chains.SUPPLIERSugarcaneBagasse &BambooI1.30 d1Refiner Hydropulp& AKD SizingC/T 1.2 sI1.50 d2Thermoform RotaryVacuum MoldC/T 1.2 sI1.80 d3Hot-Press In-MoldSmooth DryC/T 1.2 sI0.70 d4Laser Trim &Stack CountC/T 1.2 sI0.80 d5Clean Poly Sleeve& PalletC/T 1.2 sI1.50 dCUSTOMERQSR FoodserviceChains85,000 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Refiner Hydropulp & AKD Sizing1.2 s25 min94%98.8%85,000110,500 (1.30 d)61,528
2. Thermoform Rotary Vacuum Mold1.2 s40 min91%97.6%68,000127,500 (1.50 d)57,730
3. Hot-Press In-Mold Smooth Dry1.2 s45 min84%95.8%68,000153,000 (1.80 d)52,055
4. Laser Trim & Stack Count1.2 s5 min97%98.9%21,25059,500 (0.70 d)63,795
5. Clean Poly Sleeve & Pallet1.2 s8 min97%99.5%25,50068,000 (0.80 d)63,861

Key figures

Takt time
1.0 s
Lead time
7.60 d
Value-added time
6.0 s
Process cycle efficiency (PCE)
0.001%
Rolled throughput yield (RTY)
90.9%
Customer demand per day
85,000 units
Line capacity per day
52,055 units
Bottleneck
Hot-Press In-Mold Smooth Dry

Reading the bottleneck

The bottleneck is "Hot-Press In-Mold Smooth Dry": it can process 52,055 units per day against a demand of 85,000 units, so it falls short of demand by 38.8%. Once downtime and scrap are counted, its cycle time grows from 1.2 s to 1.5 s, against a takt of 1.0 s. The largest loss at this step is equipment downtime (uptime 84%), about 0.2 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.