900-Ton/Day Recycled Testliner Packaging Mill

Product family: Jumbo 5m Kraft Paper Reels.

Flow: OCC Post-Consumer Paper Bales → Drum Pulper & Plastic Screen → Twin-Wire Fourdrinier Form → Shoe Press & 48-Cylinder Dry → Starch Size Press & Rewind Reel → Jumbo Winder & Barcode Wrap → Corrugated Box Plants

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: 900-Ton/Day Recycled Testliner Packaging MillSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. OCC Post-Consumer Paper Bales → Drum Pulper & Plastic Screen (63.0 s) → Twin-Wire Fourdrinier Form (74.0 s) → Shoe Press & 48-Cylinder Dry (96.0 s) → Starch Size Press & Rewind Reel (61.0 s) → Jumbo Winder & Barcode Wrap (50.0 s) → Corrugated Box Plants.SUPPLIEROCCPost-ConsumerPaper BalesI1.30 d1Drum Pulper &Plastic ScreenC/T 63.0 sI1.50 d2Twin-WireFourdrinier FormC/T 74.0 sI1.80 d3Shoe Press &48-Cylinder DryC/T 96.0 sI0.70 d4Starch Size Press& Rewind ReelC/T 61.0 sI0.80 d5Jumbo Winder &Barcode WrapC/T 50.0 sI1.50 dCUSTOMERCorrugated BoxPlants900 / tonnes

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Drum Pulper & Plastic Screen63.0 s25 min94%98.8%9001,170 (1.30 d)1,172
2. Twin-Wire Fourdrinier Form74.0 s40 min91%97.6%7201,350 (1.50 d)936
3. Shoe Press & 48-Cylinder Dry96.0 s45 min84%95.8%7201,620 (1.80 d)651
4. Starch Size Press & Rewind Reel61.0 s5 min97%98.9%225630 (0.70 d)1,255
5. Jumbo Winder & Barcode Wrap50.0 s8 min97%99.5%270720 (0.80 d)1,533

Key figures

Takt time
90.0 s
Lead time
7.60 d
Value-added time
344 s
Process cycle efficiency (PCE)
0.056%
Rolled throughput yield (RTY)
90.9%
Customer demand per day
900 tonnes
Line capacity per day
651 tonnes
Bottleneck
Shoe Press & 48-Cylinder Dry

Reading the bottleneck

The bottleneck is "Shoe Press & 48-Cylinder Dry": it can process 651 tonnes per day against a demand of 900 tonnes, so it falls short of demand by 27.7%. Once downtime and scrap are counted, its cycle time grows from 96.0 s to 119 s, against a takt of 90.0 s. The largest loss at this step is equipment downtime (uptime 84%), about 18.3 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.