3-Ply Virgin/Bamboo Toilet & Towel Converting
Product family: 24-Roll Consumer Shrink Packs.
Flow: Jumbo Creped Tissue Reels → Twin-Unwind Micro-Emboss Glue → 1400m/min Non-Stop Rewinder → Accumulate & Dual Orbital Log Saw → Diverter Multi-Pack Wrapper → Case Pack / Shrink Bundle → Supermarkets & Away-from-Home
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Twin-Unwind Micro-Emboss Glue | 1.6 s | 25 min | 94% | 98.8% | 36,000 | 46,800 (1.30 d) | 46,146 |
| 2. 1400m/min Non-Stop Rewinder | 1.8 s | 40 min | 91% | 97.6% | 28,800 | 54,000 (1.50 d) | 38,487 |
| 3. Accumulate & Dual Orbital Log Saw | 2.4 s | 45 min | 84% | 95.8% | 28,800 | 64,800 (1.80 d) | 26,028 |
| 4. Diverter Multi-Pack Wrapper | 1.5 s | 5 min | 97% | 98.9% | 9,000 | 25,200 (0.70 d) | 51,036 |
| 5. Case Pack / Shrink Bundle | 1.3 s | 8 min | 97% | 99.5% | 10,800 | 28,800 (0.80 d) | 58,948 |
Key figures
- Takt time
- 2.3 s
- Lead time
- 7.60 d
- Value-added time
- 8.6 s
- Process cycle efficiency (PCE)
- 0.001%
- Rolled throughput yield (RTY)
- 90.9%
- Customer demand per day
- 36,000 packs
- Line capacity per day
- 26,028 packs
- Bottleneck
- Accumulate & Dual Orbital Log Saw
Reading the bottleneck
The bottleneck is "Accumulate & Dual Orbital Log Saw": it can process 26,028 packs per day against a demand of 36,000 packs, so it falls short of demand by 27.7%. Once downtime and scrap are counted, its cycle time grows from 2.4 s to 3.0 s, against a takt of 2.3 s. The largest loss at this step is equipment downtime (uptime 84%), about 0.5 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Pulp, Paper Mills & Corrugated Boxes: Pulp, Paper Mills & Corrugated Boxes
- High-Speed Corrugated E-Commerce Box Line
- 900-Ton/Day Recycled Testliner Packaging Mill
- 6-Pack Wet-Strength Beer Basket Carrier Carton
- 100% Bagasse Molded Pulp Food Clamshell Line
- Ultra-Thin 45gsm Miniature Pharma Outsert Line
- Double-Wall Aqueous-Coated Disposable Paper Cup
- BPA-Free Thermal POS Receipt & Scale Roll Line
- Watermark Cotton Paper & Hologram Security Sheet
- High-Humidity Wax-Free Export Citrus Box
- Custom Multi-Tier Printed Retail Floor Display
- Reinforced Fiberglass Water-Activated Gummed Tape