BPA-Free Thermal POS Receipt & Scale Roll Line

Product family: 80x80mm Thermal Core Slit Rolls.

Flow: Phenol-Free Jumbo Producer → 1.2m Jumbo Master Unwind → High-Speed Razor Slitter Rewind → Pre-Print Brand Back Flexo → PVC/Card Core Automatic Tuck → Shrink 5-Roll Stack & Case → Retail POS & Logistics Labels

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: BPA-Free Thermal POS Receipt & Scale Roll LineSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Phenol-Free Jumbo Producer → 1.2m Jumbo Master Unwind (1.2 s) → High-Speed Razor Slitter Rewind (1.2 s) → Pre-Print Brand Back Flexo (1.2 s) → PVC/Card Core Automatic Tuck (1.2 s) → Shrink 5-Roll Stack & Case (1.2 s) → Retail POS & Logistics Labels.SUPPLIERPhenol-FreeJumbo ProducerI1.30 d11.2m Jumbo MasterUnwindC/T 1.2 sI1.50 d2High-Speed RazorSlitter RewindC/T 1.2 sI1.80 d3Pre-Print BrandBack FlexoC/T 1.2 sI0.70 d4PVC/Card CoreAutomatic TuckC/T 1.2 sI0.80 d5Shrink 5-RollStack & CaseC/T 1.2 sI1.50 dCUSTOMERRetail POS &Logistics…54,000 / packs

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. 1.2m Jumbo Master Unwind1.2 s25 min94%98.8%54,00070,200 (1.30 d)40,632
2. High-Speed Razor Slitter Rewind1.2 s40 min91%97.6%43,20081,000 (1.50 d)37,747
3. Pre-Print Brand Back Flexo1.2 s45 min84%95.8%43,20097,200 (1.80 d)33,949
4. PVC/Card Core Automatic Tuck1.2 s5 min97%98.9%13,50037,800 (0.70 d)42,211
5. Shrink 5-Roll Stack & Case1.2 s8 min97%99.5%16,20043,200 (0.80 d)42,145

Key figures

Takt time
1.0 s
Lead time
7.60 d
Value-added time
6.0 s
Process cycle efficiency (PCE)
0.001%
Rolled throughput yield (RTY)
90.9%
Customer demand per day
54,000 packs
Line capacity per day
33,949 packs
Bottleneck
Pre-Print Brand Back Flexo

Reading the bottleneck

The bottleneck is "Pre-Print Brand Back Flexo": it can process 33,949 packs per day against a demand of 54,000 packs, so it falls short of demand by 37.1%. Once downtime and scrap are counted, its cycle time grows from 1.2 s to 1.5 s, against a takt of 1.0 s. The largest loss at this step is equipment downtime (uptime 84%), about 0.2 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.