Custom Multi-Tier Printed Retail Floor Display

Product family: Pre-Packed Supermarket FSDUs.

Flow: E/B Double-Wall Corrugated → Single-Pass Digital UV Inkjet → CNC Sample & Die-Cut → Hot-Melt Hand/Jig Structural → Co-Pack Load Tray & Sleeve → Palletize Ready-for-Aisle → FMCG Brand Promotions

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Custom Multi-Tier Printed Retail Floor DisplaySupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. E/B Double-Wall Corrugated → Single-Pass Digital UV Inkjet (44.0 s) → CNC Sample & Die-Cut (52.0 s) → Hot-Melt Hand/Jig Structural (68.0 s) → Co-Pack Load Tray & Sleeve (43.0 s) → Palletize Ready-for-Aisle (35.6 s) → FMCG Brand Promotions.SUPPLIERE/B Double-WallCorrugatedI1.30 d1Single-PassDigital UV InkjetC/T 44.0 sI1.50 d2CNC Sample &Die-CutC/T 52.0 sI1.80 d3Hot-Melt Hand/JigStructuralC/T 68.0 sI0.70 d4Co-Pack Load Tray& SleeveC/T 43.0 sI0.80 d5PalletizeReady-for-AisleC/T 35.6 sI1.50 dCUSTOMERFMCG BrandPromotions850 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Single-Pass Digital UV Inkjet44.0 s25 min94%98.8%8501,105 (1.30 d)1,108
2. CNC Sample & Die-Cut52.0 s40 min91%97.6%6801,275 (1.50 d)871
3. Hot-Melt Hand/Jig Structural68.0 s45 min84%95.8%6801,530 (1.80 d)599
4. Co-Pack Load Tray & Sleeve43.0 s5 min97%98.9%213595 (0.70 d)1,178
5. Palletize Ready-for-Aisle35.6 s8 min97%99.5%255680 (0.80 d)1,421

Key figures

Takt time
63.5 s
Lead time
7.60 d
Value-added time
243 s
Process cycle efficiency (PCE)
0.059%
Rolled throughput yield (RTY)
90.9%
Customer demand per day
850 units
Line capacity per day
599 units
Bottleneck
Hot-Melt Hand/Jig Structural

Reading the bottleneck

The bottleneck is "Hot-Melt Hand/Jig Structural": it can process 599 units per day against a demand of 850 units, so it falls short of demand by 29.5%. Once downtime and scrap are counted, its cycle time grows from 68.0 s to 84.5 s, against a takt of 63.5 s. The largest loss at this step is equipment downtime (uptime 84%), about 13.0 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.