Custom Multi-Tier Printed Retail Floor Display
Product family: Pre-Packed Supermarket FSDUs.
Flow: E/B Double-Wall Corrugated → Single-Pass Digital UV Inkjet → CNC Sample & Die-Cut → Hot-Melt Hand/Jig Structural → Co-Pack Load Tray & Sleeve → Palletize Ready-for-Aisle → FMCG Brand Promotions
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Single-Pass Digital UV Inkjet | 44.0 s | 25 min | 94% | 98.8% | 850 | 1,105 (1.30 d) | 1,108 |
| 2. CNC Sample & Die-Cut | 52.0 s | 40 min | 91% | 97.6% | 680 | 1,275 (1.50 d) | 871 |
| 3. Hot-Melt Hand/Jig Structural | 68.0 s | 45 min | 84% | 95.8% | 680 | 1,530 (1.80 d) | 599 |
| 4. Co-Pack Load Tray & Sleeve | 43.0 s | 5 min | 97% | 98.9% | 213 | 595 (0.70 d) | 1,178 |
| 5. Palletize Ready-for-Aisle | 35.6 s | 8 min | 97% | 99.5% | 255 | 680 (0.80 d) | 1,421 |
Key figures
- Takt time
- 63.5 s
- Lead time
- 7.60 d
- Value-added time
- 243 s
- Process cycle efficiency (PCE)
- 0.059%
- Rolled throughput yield (RTY)
- 90.9%
- Customer demand per day
- 850 units
- Line capacity per day
- 599 units
- Bottleneck
- Hot-Melt Hand/Jig Structural
Reading the bottleneck
The bottleneck is "Hot-Melt Hand/Jig Structural": it can process 599 units per day against a demand of 850 units, so it falls short of demand by 29.5%. Once downtime and scrap are counted, its cycle time grows from 68.0 s to 84.5 s, against a takt of 63.5 s. The largest loss at this step is equipment downtime (uptime 84%), about 13.0 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Pulp, Paper Mills & Corrugated Boxes: Pulp, Paper Mills & Corrugated Boxes
- High-Speed Corrugated E-Commerce Box Line
- 900-Ton/Day Recycled Testliner Packaging Mill
- 3-Ply Virgin/Bamboo Toilet & Towel Converting
- 6-Pack Wet-Strength Beer Basket Carrier Carton
- 100% Bagasse Molded Pulp Food Clamshell Line
- Ultra-Thin 45gsm Miniature Pharma Outsert Line
- Double-Wall Aqueous-Coated Disposable Paper Cup
- BPA-Free Thermal POS Receipt & Scale Roll Line
- Watermark Cotton Paper & Hologram Security Sheet
- High-Humidity Wax-Free Export Citrus Box
- Reinforced Fiberglass Water-Activated Gummed Tape