6-Pack Wet-Strength Beer Basket Carrier Carton

Product family: Die-Cut Litho Kraft Cartons.

Flow: SUS Virgin Kraft Paperboard → Sheet-Fed 6-Color Offset Press → UV Aqueous Scuff Varnish Coat → Flatbed Die-Cut & Strip → Multi-Point 6-Cell Folder-Glue → Automatic Tray Case Packing → Breweries & Soft Drinks

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: 6-Pack Wet-Strength Beer Basket Carrier CartonSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. SUS Virgin Kraft Paperboard → Sheet-Fed 6-Color Offset Press (1.2 s) → UV Aqueous Scuff Varnish Coat (1.2 s) → Flatbed Die-Cut & Strip (1.4 s) → Multi-Point 6-Cell Folder-Glue (1.2 s) → Automatic Tray Case Packing (1.2 s) → Breweries & Soft Drinks.SUPPLIERSUS VirginKraftPaperboardI1.30 d1Sheet-Fed 6-ColorOffset PressC/T 1.2 sI1.50 d2UV Aqueous ScuffVarnish CoatC/T 1.2 sI1.80 d3Flatbed Die-Cut &StripC/T 1.4 sI0.70 d4Multi-Point6-Cell…C/T 1.2 sI0.80 d5Automatic TrayCase PackingC/T 1.2 sI1.50 dCUSTOMERBreweries &Soft Drinks42,000 / packs

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Sheet-Fed 6-Color Offset Press1.2 s25 min94%98.8%42,00054,600 (1.30 d)40,632
2. UV Aqueous Scuff Varnish Coat1.2 s40 min91%97.6%33,60063,000 (1.50 d)37,747
3. Flatbed Die-Cut & Strip1.4 s45 min84%95.8%33,60075,600 (1.80 d)29,099
4. Multi-Point 6-Cell Folder-Glue1.2 s5 min97%98.9%10,50029,400 (0.70 d)42,211
5. Automatic Tray Case Packing1.2 s8 min97%99.5%12,60033,600 (0.80 d)42,145

Key figures

Takt time
1.3 s
Lead time
7.60 d
Value-added time
6.2 s
Process cycle efficiency (PCE)
0.002%
Rolled throughput yield (RTY)
90.9%
Customer demand per day
42,000 packs
Line capacity per day
29,099 packs
Bottleneck
Flatbed Die-Cut & Strip

Reading the bottleneck

The bottleneck is "Flatbed Die-Cut & Strip": it can process 29,099 packs per day against a demand of 42,000 packs, so it falls short of demand by 30.7%. Once downtime and scrap are counted, its cycle time grows from 1.4 s to 1.7 s, against a takt of 1.3 s. The largest loss at this step is equipment downtime (uptime 84%), about 0.3 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.