Automated Smyth-Sewn Hardcover Book Bindery
Product family: Full-Color Trade Hardbacks.
Flow: Coated Art Paper → 8-Color Heatset Web Offset → Signature Fold & Collating → Smyth-Sewn Thread Spine Bind → Hardcover Case-In & Nipping → Jacket Wrap & Shrink Pallet → Global Publishing Houses
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. 8-Color Heatset Web Offset | 1.9 s | 20 min | 96% | 98.2% | 14,400 | 25,200 (1.40 d) | 26,049 |
| 2. Signature Fold & Collating | 3.2 s | 65 min | 84% | 95.4% | 18,000 | 36,000 (2.00 d) | 12,546 |
| 3. Smyth-Sewn Thread Spine Bind | 2.4 s | 30 min | 91% | 97.8% | 14,400 | 27,000 (1.50 d) | 19,190 |
| 4. Hardcover Case-In & Nipping | 2.2 s | 15 min | 94% | 98.5% | 7,200 | 18,000 (1.00 d) | 21,780 |
| 5. Jacket Wrap & Shrink Pallet | 1.6 s | 8 min | 97% | 99.4% | 5,400 | 14,400 (0.80 d) | 31,577 |
Key figures
- Takt time
- 3.0 s
- Lead time
- 8.20 d
- Value-added time
- 11.3 s
- Process cycle efficiency (PCE)
- 0.003%
- Rolled throughput yield (RTY)
- 89.7%
- Customer demand per day
- 18,000 units
- Line capacity per day
- 12,546 units
- Bottleneck
- Signature Fold & Collating
Reading the bottleneck
The bottleneck is "Signature Fold & Collating": it can process 12,546 units per day against a demand of 18,000 units, so it falls short of demand by 30.3%. Once downtime and scrap are counted, its cycle time grows from 3.2 s to 4.0 s, against a takt of 3.0 s. The largest loss at this step is equipment downtime (uptime 84%), about 0.6 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Flexible Packaging, Labels & Luxury Print: Flexible Packaging, Labels & Luxury Print
- 10-Color Solventless Retort Stand-Up Pouch
- 360° Steam-Shrink PETG Full-Body Bottle Sleeve
- UHF RFID Encoded Retail Apparel Smart Hangtag
- Digital Press + Rotary Emboss Wine Label
- Magnetic Flocked Luxury Watch & Perfume Gift Box
- GMP Die-Cut Coated Spunbond Medical Sterile Lid
- High-Speed 2-Piece Aluminum Beverage Can Deco
- Micro-Embossed Anti-Counterfeit Excise Tax Stamp
- Variable-Data Targeted Retail Catalog Print Run
- Compostable Cornstarch E-Commerce Mailer Bag
- Spiral-Wound Food-Safe Paper Canister Tube