360° Steam-Shrink PETG Full-Body Bottle Sleeve
Product family: 9-Color Gravure Seamed Sleeves.
Flow: Shrinkable 45um PETG Film → Laser Engraved Rotogravure → High-Speed Gravure Solvent Dry → THF Solvent Center Seam Tube → 100% Splice & Seam Camera → Reel Winding & Shrink Ratio → Dairy, Craft Beer & Energy
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Laser Engraved Rotogravure | 1.2 s | 20 min | 96% | 98.2% | 96,000 | 168,000 (1.40 d) | 62,455 |
| 2. High-Speed Gravure Solvent Dry | 1.2 s | 65 min | 84% | 95.4% | 120,000 | 240,000 (2.00 d) | 51,487 |
| 3. THF Solvent Center Seam Tube | 1.2 s | 30 min | 91% | 97.8% | 96,000 | 180,000 (1.50 d) | 58,405 |
| 4. 100% Splice & Seam Camera | 1.2 s | 15 min | 94% | 98.5% | 48,000 | 120,000 (1.00 d) | 60,762 |
| 5. Reel Winding & Shrink Ratio | 1.2 s | 8 min | 97% | 99.4% | 36,000 | 96,000 (0.80 d) | 63,797 |
Key figures
- Takt time
- 0.7 s
- Lead time
- 8.20 d
- Value-added time
- 6.0 s
- Process cycle efficiency (PCE)
- 0.001%
- Rolled throughput yield (RTY)
- 89.7%
- Customer demand per day
- 120,000 units
- Line capacity per day
- 51,487 units
- Bottleneck
- High-Speed Gravure Solvent Dry
Reading the bottleneck
The bottleneck is "High-Speed Gravure Solvent Dry": it can process 51,487 units per day against a demand of 120,000 units, so it falls short of demand by 57.1%. Once downtime and scrap are counted, its cycle time grows from 1.2 s to 1.5 s, against a takt of 0.7 s. The largest loss at this step is equipment downtime (uptime 84%), about 0.2 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Flexible Packaging, Labels & Luxury Print: Flexible Packaging, Labels & Luxury Print
- 10-Color Solventless Retort Stand-Up Pouch
- Automated Smyth-Sewn Hardcover Book Bindery
- UHF RFID Encoded Retail Apparel Smart Hangtag
- Digital Press + Rotary Emboss Wine Label
- Magnetic Flocked Luxury Watch & Perfume Gift Box
- GMP Die-Cut Coated Spunbond Medical Sterile Lid
- High-Speed 2-Piece Aluminum Beverage Can Deco
- Micro-Embossed Anti-Counterfeit Excise Tax Stamp
- Variable-Data Targeted Retail Catalog Print Run
- Compostable Cornstarch E-Commerce Mailer Bag
- Spiral-Wound Food-Safe Paper Canister Tube