X-Ray Detectable Bleached Cotton Lap Sponge
Product family: Sterile OR Surgical Swabs.
Flow: Raw Bleached Cotton Gauze → Hydrogen Peroxide Bleaching → Barium Thread Heat-Weave Insert → Automatic Fold & Count Stack → Peel-Pouch Heat Seal → Steam Autoclave Sterile Cycle → Hospital Surgical Kits
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Hydrogen Peroxide Bleaching | 1.2 s | 35 min | 94% | 98.8% | 142,500 | 152,000 (1.60 d) | 61,605 |
| 2. Barium Thread Heat-Weave Insert | 1.2 s | 55 min | 90% | 97.4% | 142,500 | 171,000 (1.80 d) | 57,563 |
| 3. Automatic Fold & Count Stack | 1.2 s | 60 min | 84% | 94.8% | 114,000 | 209,000 (2.20 d) | 51,761 |
| 4. Peel-Pouch Heat Seal | 1.2 s | 25 min | 93% | 98.2% | 57,000 | 114,000 (1.20 d) | 59,742 |
| 5. Steam Autoclave Sterile Cycle | 1.2 s | 10 min | 97% | 99.1% | 38,000 | 85,500 (0.90 d) | 63,684 |
Key figures
- Takt time
- 0.9 s
- Lead time
- 9.50 d
- Value-added time
- 6.0 s
- Process cycle efficiency (PCE)
- 0.001%
- Rolled throughput yield (RTY)
- 88.8%
- Customer demand per day
- 95,000 packs
- Line capacity per day
- 51,761 packs
- Bottleneck
- Automatic Fold & Count Stack
Reading the bottleneck
The bottleneck is "Automatic Fold & Count Stack": it can process 51,761 packs per day against a demand of 95,000 packs, so it falls short of demand by 45.5%. Once downtime and scrap are counted, its cycle time grows from 1.2 s to 1.5 s, against a takt of 0.9 s. The largest loss at this step is equipment downtime (uptime 84%), about 0.2 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Spinning, Weaving, Dyeing & Tech Textiles: Spinning, Weaving, Dyeing & Tech Textiles
- 100-Ton/Day Combed Ring-Spun Organic Cotton Mill
- Rope-Dyed Indigo & Air-Jet Shuttleless Denim Mill
- Pad-Steam Continuous Reactive Cotton Dye Range
- Meta-Aramid Firefighter Turnout Outer Shell Roll
- Triple-Beam SMS Non-Woven Hygiene Fabric Roll
- Unidirectional Wind-Spar Carbon Tow Prepreg Line
- Needlepunch Recycled PET Automotive Trunk Felt
- Split-Bicomponent Warp-Knit Microfiber Roll
- 1200g High-Tensile Geosynthetic Drainage Felt
- Closed-Loop NMMO Lyocell Regenerated Cellulosic
- 2116 Electrical-Grade Woven E-Glass Fabric Roll