Closed-Loop NMMO Lyocell Regenerated Cellulosic

Product family: Eucalyptus Sustainable Filament.

Flow: FSC Eucalyptus Dissolving Pulp → Shred Pulp & NMMO Vacuum Diss → Dry-Jet Wet Spin Air Gap → Solvent Recovery Wash Cascade → Finish Bath, Crimp & Cut Tow → Bale Press & Tenacity Lab → Fashion & Home Bedding Mills

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Closed-Loop NMMO Lyocell Regenerated CellulosicSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. FSC Eucalyptus Dissolving Pulp → Shred Pulp & NMMO Vacuum Diss (709 s) → Dry-Jet Wet Spin Air Gap (851 s) → Solvent Recovery Wash Cascade (1,094 s) → Finish Bath, Crimp & Cut Tow (770 s) → Bale Press & Tenacity Lab (567 s) → Fashion & Home Bedding Mills.SUPPLIERFSC EucalyptusDissolving PulpI1.60 d1Shred Pulp & NMMOVacuum DissC/T 709 sI1.80 d2Dry-Jet Wet SpinAir GapC/T 851 sI2.20 d3Solvent RecoveryWash CascadeC/T 1,094 sI1.20 d4Finish Bath,Crimp & Cut TowC/T 770 sI0.90 d5Bale Press &Tenacity LabC/T 567 sI1.80 dCUSTOMERFashion & HomeBedding Mills80 / tonnes

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Shred Pulp & NMMO Vacuum Diss709 s35 min94%98.8%120128 (1.60 d)104
2. Dry-Jet Wet Spin Air Gap851 s55 min90%97.4%120144 (1.80 d)81
3. Solvent Recovery Wash Cascade1,094 s60 min84%94.8%96176 (2.20 d)57
4. Finish Bath, Crimp & Cut Tow770 s25 min93%98.2%4896 (1.20 d)93
5. Bale Press & Tenacity Lab567 s10 min97%99.1%3272 (0.90 d)135

Key figures

Takt time
1,013 s
Lead time
9.55 d
Value-added time
3,991 s
Process cycle efficiency (PCE)
0.52%
Rolled throughput yield (RTY)
88.8%
Customer demand per day
80 tonnes
Line capacity per day
57 tonnes
Bottleneck
Solvent Recovery Wash Cascade

Reading the bottleneck

The bottleneck is "Solvent Recovery Wash Cascade": it can process 57 tonnes per day against a demand of 80 tonnes, so it falls short of demand by 29.0%. Once downtime and scrap are counted, its cycle time grows from 1,094 s to 1,374 s, against a takt of 1,013 s. The largest loss at this step is equipment downtime (uptime 84%), about 208 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.

Other scenarios in this family

More scenarios of Spinning, Weaving, Dyeing & Tech Textiles: Spinning, Weaving, Dyeing & Tech Textiles