Split-Bicomponent Warp-Knit Microfiber Roll
Product family: Cleanroom Optics Wiping Cloths.
Flow: 70/30 PET-PA Micro-Filaments → Tricot Warp Knit → Alkaline Fiber Split Shrinkage → Laser Sealed-Edge Ultrasonic → DI-Water Class-100 Launder → Particle Shake Count Packaging → Semicon & Cleanroom Supply
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Tricot Warp Knit | 788 s | 35 min | 94% | 98.8% | 72 | 77 (1.60 d) | 62 |
| 2. Alkaline Fiber Split Shrinkage | 945 s | 55 min | 90% | 97.4% | 72 | 86 (1.79 d) | 48 |
| 3. Laser Sealed-Edge Ultrasonic | 1,215 s | 60 min | 84% | 94.8% | 58 | 106 (2.21 d) | 33 |
| 4. DI-Water Class-100 Launder | 855 s | 25 min | 93% | 98.2% | 29 | 58 (1.21 d) | 55 |
| 5. Particle Shake Count Packaging | 630 s | 10 min | 97% | 99.1% | 19 | 43 (0.90 d) | 80 |
Key figures
- Takt time
- 1,125 s
- Lead time
- 9.58 d
- Value-added time
- 4,433 s
- Process cycle efficiency (PCE)
- 0.86%
- Rolled throughput yield (RTY)
- 88.8%
- Customer demand per day
- 48 tonnes
- Line capacity per day
- 33 tonnes
- Bottleneck
- Laser Sealed-Edge Ultrasonic
Reading the bottleneck
The bottleneck is "Laser Sealed-Edge Ultrasonic": it can process 33 tonnes per day against a demand of 48 tonnes, so it falls short of demand by 30.3%. Once downtime and scrap are counted, its cycle time grows from 1,215 s to 1,526 s, against a takt of 1,125 s. The largest loss at this step is equipment downtime (uptime 84%), about 231 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Spinning, Weaving, Dyeing & Tech Textiles: Spinning, Weaving, Dyeing & Tech Textiles
- 100-Ton/Day Combed Ring-Spun Organic Cotton Mill
- Rope-Dyed Indigo & Air-Jet Shuttleless Denim Mill
- Pad-Steam Continuous Reactive Cotton Dye Range
- Meta-Aramid Firefighter Turnout Outer Shell Roll
- Triple-Beam SMS Non-Woven Hygiene Fabric Roll
- Unidirectional Wind-Spar Carbon Tow Prepreg Line
- Needlepunch Recycled PET Automotive Trunk Felt
- 1200g High-Tensile Geosynthetic Drainage Felt
- Closed-Loop NMMO Lyocell Regenerated Cellulosic
- X-Ray Detectable Bleached Cotton Lap Sponge
- 2116 Electrical-Grade Woven E-Glass Fabric Roll