Modular Cabinetry & Millwork Line

Product family: Kitchen & Office Modular Cabinets.

Flow: FSC Timber & Hinge Hardware → CNC Panel Nesting Cut → Edge Banding & Glue → Lacquer Booth & UV Cure → Dowel Boring & Fittings → Flat-Pack & Corner Guard → Showrooms & B2B Contractors

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Modular Cabinetry & Millwork LineSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. FSC Timber & Hinge Hardware → CNC Panel Nesting Cut (61.0 s) → Edge Banding & Glue (70.0 s) → Lacquer Booth & UV Cure (96.0 s) → Dowel Boring & Fittings (67.0 s) → Flat-Pack & Corner Guard (50.0 s) → Showrooms & B2B Contractors.SUPPLIERFSC Timber &Hinge HardwareI1.60 d1CNC Panel NestingCutC/T 61.0 sI1.40 d2Edge Banding &GlueC/T 70.0 sI2.00 d3Lacquer Booth &UV CureC/T 96.0 sI1.00 d4Dowel Boring &FittingsC/T 67.0 sI0.80 d5Flat-Pack &Corner GuardC/T 50.0 sI1.40 dCUSTOMERShowrooms & B2BContractors300 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. CNC Panel Nesting Cut61.0 s18 min95%98.8%300480 (1.60 d)399
2. Edge Banding & Glue70.0 s22 min93%98.0%180420 (1.40 d)323
3. Lacquer Booth & UV Cure96.0 s35 min85%94.0%300600 (2.00 d)207
4. Dowel Boring & Fittings67.0 s15 min93%97.6%120300 (1.00 d)335
5. Flat-Pack & Corner Guard50.0 s8 min97%99.3%90240 (0.80 d)489

Key figures

Takt time
90.0 s
Lead time
8.21 d
Value-added time
344 s
Process cycle efficiency (PCE)
0.16%
Rolled throughput yield (RTY)
88.2%
Customer demand per day
300 units
Line capacity per day
207 units
Bottleneck
Lacquer Booth & UV Cure

Reading the bottleneck

The bottleneck is "Lacquer Booth & UV Cure": it can process 207 units per day against a demand of 300 units, so it falls short of demand by 30.9%. Once downtime and scrap are counted, its cycle time grows from 96.0 s to 120 s, against a takt of 90.0 s. The largest loss at this step is equipment downtime (uptime 85%), about 16.9 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.