Modular Flagship Cosmetics Store Gondola Display
Product family: Illuminated Metal-Wood Fixtures.
Flow: Powder Steel & Solid Surface → Laser Steel & Solid Surface Milling → Wood Carcass Veneer Assembly → Low-Voltage 24V LED Harness → Power-Up Photometric Check → Crate Cushioning & Site Tag → Global Beauty Flagship Stores
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Laser Steel & Solid Surface Milling | 408 s | 18 min | 95% | 98.8% | 45 | 72 (1.60 d) | 60 |
| 2. Wood Carcass Veneer Assembly | 468 s | 22 min | 93% | 98.0% | 27 | 63 (1.40 d) | 48 |
| 3. Low-Voltage 24V LED Harness | 642 s | 35 min | 85% | 94.0% | 45 | 90 (2.00 d) | 31 |
| 4. Power-Up Photometric Check | 444 s | 15 min | 93% | 97.6% | 18 | 45 (1.00 d) | 51 |
| 5. Crate Cushioning & Site Tag | 336 s | 8 min | 97% | 99.3% | 14 | 36 (0.80 d) | 73 |
Key figures
- Takt time
- 600 s
- Lead time
- 8.29 d
- Value-added time
- 2,298 s
- Process cycle efficiency (PCE)
- 1.0%
- Rolled throughput yield (RTY)
- 88.2%
- Customer demand per day
- 45 units
- Line capacity per day
- 31 units
- Bottleneck
- Low-Voltage 24V LED Harness
Reading the bottleneck
The bottleneck is "Low-Voltage 24V LED Harness": it can process 31 units per day against a demand of 45 units, so it falls short of demand by 31.1%. Once downtime and scrap are counted, its cycle time grows from 642 s to 804 s, against a takt of 600 s. The largest loss at this step is equipment downtime (uptime 85%), about 113 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Furniture, Millwork & Joinery: Furniture, Millwork & Joinery
- Modular Cabinetry & Millwork Line
- Modular Beech-Frame Upholstered Sectional Sofa
- Solid French Oak Butterfly-Extension Dining Table
- BIFMA Certified Mesh Ergonomic Task Chair
- Wood-Veneer Slatted Recycled PET Acoustic Wall
- 3-Layer Engineered Oak Click-Lock Parquet Line
- EI-30 Fire-Rated Acoustic Flush Interior Door
- Hospitality Turnkey Guestroom Casegoods Fit-Out
- FSC Teak & All-Weather Rope Patio Lounger
- Tip-Up Fire-Retardant Auditorium Cinema Seat
- Water-Based Non-Toxic EN-71 Wooden Toy Kitchen