Solid French Oak Butterfly-Extension Dining Table

Product family: Oil-Finished Hardwood Tables.

Flow: PEFC French White Oak → Rip, Finger-Joint & Press Glue → 5-Axis CNC Bevel & Slide Groove → Wide-Belt Calibrating Sander → Oil-Wax Roll & Cure → Felt Pad, Hardware Kit & Box → Home & Design Retailers

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Solid French Oak Butterfly-Extension Dining TableSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. PEFC French White Oak → Rip, Finger-Joint & Press Glue (282 s) → 5-Axis CNC Bevel & Slide Groove (324 s) → Wide-Belt Calibrating Sander (444 s) → Oil-Wax Roll & Cure (307 s) → Felt Pad, Hardware Kit & Box (233 s) → Home & Design Retailers.SUPPLIERPEFC FrenchWhite OakI1.60 d1Rip, Finger-Joint& Press GlueC/T 282 sI1.40 d25-Axis CNC Bevel& Slide GrooveC/T 324 sI2.00 d3Wide-BeltCalibrating…C/T 444 sI1.00 d4Oil-Wax Roll &CureC/T 307 sI0.80 d5Felt Pad,Hardware Kit &…C/T 233 sI1.40 dCUSTOMERHome & DesignRetailers65 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Rip, Finger-Joint & Press Glue282 s18 min95%98.8%65104 (1.60 d)86
2. 5-Axis CNC Bevel & Slide Groove324 s22 min93%98.0%3991 (1.40 d)70
3. Wide-Belt Calibrating Sander444 s35 min85%94.0%65130 (2.00 d)45
4. Oil-Wax Roll & Cure307 s15 min93%97.6%2665 (1.00 d)73
5. Felt Pad, Hardware Kit & Box233 s8 min97%99.3%2052 (0.80 d)105

Key figures

Takt time
415 s
Lead time
8.26 d
Value-added time
1,590 s
Process cycle efficiency (PCE)
0.71%
Rolled throughput yield (RTY)
88.2%
Customer demand per day
65 units
Line capacity per day
45 units
Bottleneck
Wide-Belt Calibrating Sander

Reading the bottleneck

The bottleneck is "Wide-Belt Calibrating Sander": it can process 45 units per day against a demand of 65 units, so it falls short of demand by 31.1%. Once downtime and scrap are counted, its cycle time grows from 444 s to 556 s, against a takt of 415 s. The largest loss at this step is equipment downtime (uptime 85%), about 78.4 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.