3-Layer Engineered Oak Click-Lock Parquet Line

Product family: Brushed UV-Oiled Plank Floor.

Flow: 4mm European Oak Top Lamella → Lamella Frame Saw & Calibrate → 3-Layer Cold/Hot Press Laminate → Double-End Tenoner Click Mill → Wire Brush & 7-Coat UV Oil → Bundle Wrap & Moisture Check → Building & Flooring Wholesale

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: 3-Layer Engineered Oak Click-Lock Parquet LineSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. 4mm European Oak Top Lamella → Lamella Frame Saw & Calibrate (15.3 s) → 3-Layer Cold/Hot Press Laminate (17.6 s) → Double-End Tenoner Click Mill (24.1 s) → Wire Brush & 7-Coat UV Oil (16.6 s) → Bundle Wrap & Moisture Check (12.6 s) → Building & Flooring Wholesale.SUPPLIER4mm EuropeanOak Top LamellaI1.60 d1Lamella Frame Saw& CalibrateC/T 15.3 sI1.40 d23-Layer Cold/HotPress LaminateC/T 17.6 sI2.00 d3Double-EndTenoner Click…C/T 24.1 sI1.00 d4Wire Brush &7-Coat UV OilC/T 16.6 sI0.80 d5Bundle Wrap &Moisture CheckC/T 12.6 sI1.40 dCUSTOMERBuilding &Flooring…2,400 / parts

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Lamella Frame Saw & Calibrate15.3 s18 min95%98.8%2,4003,840 (1.60 d)3,246
2. 3-Layer Cold/Hot Press Laminate17.6 s22 min93%98.0%1,4403,360 (1.40 d)2,682
3. Double-End Tenoner Click Mill24.1 s35 min85%94.0%2,4004,800 (2.00 d)1,721
4. Wire Brush & 7-Coat UV Oil16.6 s15 min93%97.6%9602,400 (1.00 d)2,830
5. Bundle Wrap & Moisture Check12.6 s8 min97%99.3%7201,920 (0.80 d)4,006

Key figures

Takt time
22.5 s
Lead time
8.20 d
Value-added time
86.2 s
Process cycle efficiency (PCE)
0.019%
Rolled throughput yield (RTY)
88.2%
Customer demand per day
2,400 parts
Line capacity per day
1,721 parts
Bottleneck
Double-End Tenoner Click Mill

Reading the bottleneck

The bottleneck is "Double-End Tenoner Click Mill": it can process 1,721 parts per day against a demand of 2,400 parts, so it falls short of demand by 28.3%. Once downtime and scrap are counted, its cycle time grows from 24.1 s to 30.2 s, against a takt of 22.5 s. The largest loss at this step is equipment downtime (uptime 85%), about 4.3 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.