Industrial Hemp Bast Fiber & Hurd Decortication

Product family: Bio-Composite & Hempcrete.

Flow: Dew-Retted Hemp Round Bales → Round Bale Unwind & Cutter → Hammer-Mill & Pin-Roller Decort → Air Classifier Bast / Hurd Sep → Fiber Cleaning & Dust Cyclones → Compressed 400kg Textile Bale → Auto Composites & Hempcrete

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Industrial Hemp Bast Fiber & Hurd DecorticationSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Dew-Retted Hemp Round Bales → Round Bale Unwind & Cutter (765 s) → Hammer-Mill & Pin-Roller Decort (945 s) → Air Classifier Bast / Hurd Sep (1,204 s) → Fiber Cleaning & Dust Cyclones (833 s) → Compressed 400kg Textile Bale (630 s) → Auto Composites & Hempcrete.SUPPLIERDew-Retted HempRound BalesI0.90 d1Round Bale Unwind& CutterC/T 765 sI1.50 d2Hammer-Mill &Pin-Roller DecortC/T 945 sI2.00 d3Air ClassifierBast / Hurd SepC/T 1,204 sI1.10 d4Fiber Cleaning &Dust CyclonesC/T 833 sI1.00 d5Compressed 400kgTextile BaleC/T 630 sI1.50 dCUSTOMERAuto Composites& Hempcrete48 / tonnes

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Round Bale Unwind & Cutter765 s12 min94%98.2%2443 (0.90 d)63
2. Hammer-Mill & Pin-Roller Decort945 s20 min91%97.1%2972 (1.50 d)49
3. Air Classifier Bast / Hurd Sep1,204 s35 min84%95.5%3896 (2.00 d)34
4. Fiber Cleaning & Dust Cyclones833 s15 min93%98.1%1953 (1.10 d)57
5. Compressed 400kg Textile Bale630 s10 min97%99.3%1448 (1.00 d)79

Key figures

Takt time
1,125 s
Lead time
8.08 d
Value-added time
4,377 s
Process cycle efficiency (PCE)
1.0%
Rolled throughput yield (RTY)
88.7%
Customer demand per day
48 tonnes
Line capacity per day
34 tonnes
Bottleneck
Air Classifier Bast / Hurd Sep

Reading the bottleneck

The bottleneck is "Air Classifier Bast / Hurd Sep": it can process 34 tonnes per day against a demand of 48 tonnes, so it falls short of demand by 28.7%. Once downtime and scrap are counted, its cycle time grows from 1,204 s to 1,501 s, against a takt of 1,125 s. The largest loss at this step is equipment downtime (uptime 84%), about 229 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.