Centrifugal Raw Monofloral Honey Uncap & Jar

Product family: Moisture-Verified Glass Jars.

Flow: Migratory Apiary Supers → Warm Room Comb Conditioning → Oscillating Knife Uncapper → 80-Frame Radial Extractor Spin → 200um Gravity Settling Sump → Refractometer & Vacuum Jar → Specialty Retail & Export

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Centrifugal Raw Monofloral Honey Uncap & JarSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Migratory Apiary Supers → Warm Room Comb Conditioning (4.2 s) → Oscillating Knife Uncapper (5.3 s) → 80-Frame Radial Extractor Spin (6.9 s) → 200um Gravity Settling Sump (4.6 s) → Refractometer & Vacuum Jar (3.5 s) → Specialty Retail & Export.SUPPLIERMigratoryApiary SupersI0.90 d1Warm Room CombConditioningC/T 4.2 sI1.20 d2Oscillating KnifeUncapperC/T 5.3 sI1.00 d380-Frame RadialExtractor SpinC/T 6.9 sI0.50 d4200um GravitySettling SumpC/T 4.6 sI0.40 d5Refractometer &Vacuum JarC/T 3.5 sI0.50 dCUSTOMERSpecialtyRetail & Export4,200 / packs

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Warm Room Comb Conditioning4.2 s12 min95%97.8%2,1003,780 (0.90 d)5,654
2. Oscillating Knife Uncapper5.3 s15 min93%96.8%2,1005,040 (1.20 d)4,280
3. 80-Frame Radial Extractor Spin6.9 s25 min85%94.5%1,2604,200 (1.00 d)2,561
4. 200um Gravity Settling Sump4.6 s6 min96%98.8%8402,100 (0.50 d)5,196
5. Refractometer & Vacuum Jar3.5 s8 min97%99.4%8401,680 (0.40 d)6,777

Key figures

Takt time
6.4 s
Lead time
4.50 d
Value-added time
24.5 s
Process cycle efficiency (PCE)
0.020%
Rolled throughput yield (RTY)
87.9%
Customer demand per day
4,200 packs
Line capacity per day
2,561 packs
Bottleneck
80-Frame Radial Extractor Spin

Reading the bottleneck

The bottleneck is "80-Frame Radial Extractor Spin": it can process 2,561 packs per day against a demand of 4,200 packs, so it falls short of demand by 39.0%. Once downtime and scrap are counted, its cycle time grows from 6.9 s to 8.6 s, against a takt of 6.4 s. The largest loss at this step is equipment downtime (uptime 85%), about 1.2 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.