Automated Grafted Tomato & Pepper Plug Nursery

Product family: Disease-Free Grafted Seedlings.

Flow: Rootstock & Scion Seeds → Drum Seeder & Mist Chamber → Robot Grafting Cut & Clip → 95%-RH Healing Chamber Callus → Boom Irrigation & Hardening → Roll-Rack Climate Van Ship → Commercial Greenhouses

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Automated Grafted Tomato & Pepper Plug NurserySupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Rootstock & Scion Seeds → Drum Seeder & Mist Chamber (1.2 s) → Robot Grafting Cut & Clip (1.2 s) → 95%-RH Healing Chamber Callus (1.6 s) → Boom Irrigation & Hardening (1.2 s) → Roll-Rack Climate Van Ship (1.2 s) → Commercial Greenhouses.SUPPLIERRootstock &Scion SeedsI0.90 d1Drum Seeder &Mist ChamberC/T 1.2 sI1.20 d2Robot GraftingCut & ClipC/T 1.2 sI1.00 d395%-RH HealingChamber CallusC/T 1.6 sI0.50 d4Boom Irrigation &HardeningC/T 1.2 sI0.40 d5Roll-Rack ClimateVan ShipC/T 1.2 sI0.50 dCUSTOMERCommercialGreenhouses18,000 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Drum Seeder & Mist Chamber1.2 s12 min95%97.8%9,00016,200 (0.90 d)19,790
2. Robot Grafting Cut & Clip1.2 s15 min93%96.8%9,00021,600 (1.20 d)18,905
3. 95%-RH Healing Chamber Callus1.6 s25 min85%94.5%5,40018,000 (1.00 d)11,045
4. Boom Irrigation & Hardening1.2 s6 min96%98.8%3,6009,000 (0.50 d)19,918
5. Roll-Rack Climate Van Ship1.2 s8 min97%99.4%3,6007,200 (0.40 d)19,766

Key figures

Takt time
1.5 s
Lead time
4.50 d
Value-added time
6.4 s
Process cycle efficiency (PCE)
0.005%
Rolled throughput yield (RTY)
87.9%
Customer demand per day
18,000 units
Line capacity per day
11,045 units
Bottleneck
95%-RH Healing Chamber Callus

Reading the bottleneck

The bottleneck is "95%-RH Healing Chamber Callus": it can process 11,045 units per day against a demand of 18,000 units, so it falls short of demand by 38.6%. Once downtime and scrap are counted, its cycle time grows from 1.6 s to 2.0 s, against a takt of 1.5 s. The largest loss at this step is equipment downtime (uptime 85%), about 0.3 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.