Controlled-Atmosphere (CA) Apple Defect Line

Product family: 18kg Tray & Polybag Apples.

Flow: 1% O2 CA Storage Rooms → Water Flume Gentle Bin Dump → Water Channel Wax & Dry → Internal Browning NIR Scanner → 12-Drop Sizing Flume Lanes → Molded Pulp Tray Carton Auto → National & Export Grocers

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Controlled-Atmosphere (CA) Apple Defect LineSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. 1% O2 CA Storage Rooms → Water Flume Gentle Bin Dump (21.6 s) → Water Channel Wax & Dry (26.3 s) → Internal Browning NIR Scanner (36.1 s) → 12-Drop Sizing Flume Lanes (27.7 s) → Molded Pulp Tray Carton Auto (18.9 s) → National & Export Grocers.SUPPLIER1% O2 CAStorage RoomsI0.80 d1Water FlumeGentle Bin DumpC/T 21.6 sI0.70 d2Water Channel Wax& DryC/T 26.3 sI1.20 d3Internal BrowningNIR ScannerC/T 36.1 sI0.90 d412-Drop SizingFlume LanesC/T 27.7 sI0.60 d5Molded Pulp TrayCarton AutoC/T 18.9 sI0.70 dCUSTOMERNational &Export Grocers1,600 / crates

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Water Flume Gentle Bin Dump21.6 s15 min94%97.8%8001,280 (0.80 d)2,222
2. Water Channel Wax & Dry26.3 s12 min93%98.4%6401,120 (0.70 d)1,816
3. Internal Browning NIR Scanner36.1 s28 min84%93.0%9601,920 (1.20 d)1,108
4. 12-Drop Sizing Flume Lanes27.7 s10 min93%98.4%4801,440 (0.90 d)1,718
5. Molded Pulp Tray Carton Auto18.9 s8 min97%99.2%480960 (0.60 d)2,668

Key figures

Takt time
33.8 s
Lead time
4.90 d
Value-added time
131 s
Process cycle efficiency (PCE)
0.049%
Rolled throughput yield (RTY)
87.4%
Customer demand per day
1,600 crates
Line capacity per day
1,108 crates
Bottleneck
Internal Browning NIR Scanner

Reading the bottleneck

The bottleneck is "Internal Browning NIR Scanner": it can process 1,108 crates per day against a demand of 1,600 crates, so it falls short of demand by 30.8%. Once downtime and scrap are counted, its cycle time grows from 36.1 s to 46.2 s, against a takt of 33.8 s. The largest loss at this step is equipment downtime (uptime 84%), about 6.9 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.

Other scenarios in this family

More scenarios of Agri-Food Harvest & Export Packhouses: Agri-Food Harvest & Export Packhouses