Hass Avocado Hydro-Cool & Dry-Matter Export

Product family: 4kg Ripening Ready Trays.

Flow: Coastal Avocado Estates → Hydro-Cool Core Temp Pull → Brushing & Laser Trace Etch → NIR Dry-Matter Density Sort → Soft-Cup Tray Automated Pack → 5°C Controlled-Atmosphere Ship → European Grocery Ripeners

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Hass Avocado Hydro-Cool & Dry-Matter ExportSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Coastal Avocado Estates → Hydro-Cool Core Temp Pull (14.4 s) → Brushing & Laser Trace Etch (17.6 s) → NIR Dry-Matter Density Sort (24.1 s) → Soft-Cup Tray Automated Pack (18.4 s) → 5°C Controlled-Atmosphere Ship (12.6 s) → European Grocery Ripeners.SUPPLIERCoastal AvocadoEstatesI0.80 d1Hydro-Cool CoreTemp PullC/T 14.4 sI0.70 d2Brushing & LaserTrace EtchC/T 17.6 sI1.20 d3NIR Dry-MatterDensity SortC/T 24.1 sI0.90 d4Soft-Cup TrayAutomated PackC/T 18.4 sI0.60 d55°CControlled-Atmos…C/T 12.6 sI0.70 dCUSTOMEREuropeanGrocery…2,400 / crates

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Hydro-Cool Core Temp Pull14.4 s15 min94%97.8%1,2001,920 (0.80 d)3,333
2. Brushing & Laser Trace Etch17.6 s12 min93%98.4%9601,680 (0.70 d)2,714
3. NIR Dry-Matter Density Sort24.1 s28 min84%93.0%1,4402,880 (1.20 d)1,660
4. Soft-Cup Tray Automated Pack18.4 s10 min93%98.4%7202,160 (0.90 d)2,586
5. 5°C Controlled-Atmosphere Ship12.6 s8 min97%99.2%7201,440 (0.60 d)4,002

Key figures

Takt time
22.5 s
Lead time
4.90 d
Value-added time
87.1 s
Process cycle efficiency (PCE)
0.033%
Rolled throughput yield (RTY)
87.4%
Customer demand per day
2,400 crates
Line capacity per day
1,660 crates
Bottleneck
NIR Dry-Matter Density Sort

Reading the bottleneck

The bottleneck is "NIR Dry-Matter Density Sort": it can process 1,660 crates per day against a demand of 2,400 crates, so it falls short of demand by 30.8%. Once downtime and scrap are counted, its cycle time grows from 24.1 s to 30.8 s, against a takt of 22.5 s. The largest loss at this step is equipment downtime (uptime 84%), about 4.6 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.