Hass Avocado Hydro-Cool & Dry-Matter Export
Product family: 4kg Ripening Ready Trays.
Flow: Coastal Avocado Estates → Hydro-Cool Core Temp Pull → Brushing & Laser Trace Etch → NIR Dry-Matter Density Sort → Soft-Cup Tray Automated Pack → 5°C Controlled-Atmosphere Ship → European Grocery Ripeners
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Hydro-Cool Core Temp Pull | 14.4 s | 15 min | 94% | 97.8% | 1,200 | 1,920 (0.80 d) | 3,333 |
| 2. Brushing & Laser Trace Etch | 17.6 s | 12 min | 93% | 98.4% | 960 | 1,680 (0.70 d) | 2,714 |
| 3. NIR Dry-Matter Density Sort | 24.1 s | 28 min | 84% | 93.0% | 1,440 | 2,880 (1.20 d) | 1,660 |
| 4. Soft-Cup Tray Automated Pack | 18.4 s | 10 min | 93% | 98.4% | 720 | 2,160 (0.90 d) | 2,586 |
| 5. 5°C Controlled-Atmosphere Ship | 12.6 s | 8 min | 97% | 99.2% | 720 | 1,440 (0.60 d) | 4,002 |
Key figures
- Takt time
- 22.5 s
- Lead time
- 4.90 d
- Value-added time
- 87.1 s
- Process cycle efficiency (PCE)
- 0.033%
- Rolled throughput yield (RTY)
- 87.4%
- Customer demand per day
- 2,400 crates
- Line capacity per day
- 1,660 crates
- Bottleneck
- NIR Dry-Matter Density Sort
Reading the bottleneck
The bottleneck is "NIR Dry-Matter Density Sort": it can process 1,660 crates per day against a demand of 2,400 crates, so it falls short of demand by 30.8%. Once downtime and scrap are counted, its cycle time grows from 24.1 s to 30.8 s, against a takt of 22.5 s. The largest loss at this step is equipment downtime (uptime 84%), about 4.6 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Agri-Food Harvest & Export Packhouses: Agri-Food Harvest & Export Packhouses
- Fresh Produce Optical Grading & Export Pack
- Glasshouse Truss Tomato Optical Color & Pack
- Soft-Touch Air-Cushion Blueberry Clamshell Line
- Optical Defect Wash, Size & Net-Bag Potato Line
- Medjool Date Ultrasonic Mist & Window Box Line
- Triple-Wash Ready-to-Eat Baby Spinach Pillow Bag
- Laser & X-Ray Almond Hulling, Shelling & Pack
- Controlled-Atmosphere (CA) Apple Defect Line
- Living & Cut Fresh Herb Sleeve & Clamshell Line
- 2-Hr Field-to-Cooler Strawberry Punnet Line
- Sulfur-Pad Export Seedless Table Grape Pack