Laser & X-Ray Almond Hulling, Shelling & Pack
Product family: Extra Grade #1 Kernel Cartons.
Flow: Orchard Sweeper Trailers → De-Twig & Shear-Roll Huller → Gravity Air-Leg Shell Sep → Laser Color & Chip Optical → Pasteurization Steam Chamber → Vacuum 50lb Carton Seal → Confectionery & Milk Makers
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. De-Twig & Shear-Roll Huller | 823 s | 15 min | 94% | 97.8% | 21 | 34 (0.81 d) | 58 |
| 2. Gravity Air-Leg Shell Sep | 1,003 s | 12 min | 93% | 98.4% | 17 | 29 (0.69 d) | 48 |
| 3. Laser Color & Chip Optical | 1,376 s | 28 min | 84% | 93.0% | 25 | 50 (1.19 d) | 29 |
| 4. Pasteurization Steam Chamber | 1,054 s | 10 min | 93% | 98.4% | 13 | 38 (0.90 d) | 45 |
| 5. Vacuum 50lb Carton Seal | 720 s | 8 min | 97% | 99.2% | 13 | 25 (0.60 d) | 70 |
Key figures
- Takt time
- 1,286 s
- Lead time
- 4.97 d
- Value-added time
- 4,976 s
- Process cycle efficiency (PCE)
- 1.9%
- Rolled throughput yield (RTY)
- 87.4%
- Customer demand per day
- 42 tonnes
- Line capacity per day
- 29 tonnes
- Bottleneck
- Laser Color & Chip Optical
Reading the bottleneck
The bottleneck is "Laser Color & Chip Optical": it can process 29 tonnes per day against a demand of 42 tonnes, so it falls short of demand by 30.8%. Once downtime and scrap are counted, its cycle time grows from 1,376 s to 1,761 s, against a takt of 1,286 s. The largest loss at this step is equipment downtime (uptime 84%), about 262 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Agri-Food Harvest & Export Packhouses: Agri-Food Harvest & Export Packhouses
- Fresh Produce Optical Grading & Export Pack
- Hass Avocado Hydro-Cool & Dry-Matter Export
- Glasshouse Truss Tomato Optical Color & Pack
- Soft-Touch Air-Cushion Blueberry Clamshell Line
- Optical Defect Wash, Size & Net-Bag Potato Line
- Medjool Date Ultrasonic Mist & Window Box Line
- Triple-Wash Ready-to-Eat Baby Spinach Pillow Bag
- Controlled-Atmosphere (CA) Apple Defect Line
- Living & Cut Fresh Herb Sleeve & Clamshell Line
- 2-Hr Field-to-Cooler Strawberry Punnet Line
- Sulfur-Pad Export Seedless Table Grape Pack