Soft-Touch Air-Cushion Blueberry Clamshell Line
Product family: 125g Recycled PET Punnets.
Flow: Early Morning Hand-Pickers → 2°C Rapid Pre-Cool Blast → Gentle Soft-Drop Blower Clean → Optical Soft-Berry/Color Kick → 12-Head Rotary Clamshell Fill → Label, Checkweigh & Pallet → Air & Retail Supermarkets
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. 2°C Rapid Pre-Cool Blast | 3.6 s | 15 min | 94% | 97.8% | 4,750 | 7,600 (0.80 d) | 13,330 |
| 2. Gentle Soft-Drop Blower Clean | 4.4 s | 12 min | 93% | 98.4% | 3,800 | 6,650 (0.70 d) | 10,857 |
| 3. Optical Soft-Berry/Color Kick | 6.1 s | 28 min | 84% | 93.0% | 5,700 | 11,400 (1.20 d) | 6,557 |
| 4. 12-Head Rotary Clamshell Fill | 4.7 s | 10 min | 93% | 98.4% | 2,850 | 8,550 (0.90 d) | 10,125 |
| 5. Label, Checkweigh & Pallet | 3.2 s | 8 min | 97% | 99.2% | 2,850 | 5,700 (0.60 d) | 15,757 |
Key figures
- Takt time
- 5.7 s
- Lead time
- 4.90 d
- Value-added time
- 22.0 s
- Process cycle efficiency (PCE)
- 0.008%
- Rolled throughput yield (RTY)
- 87.4%
- Customer demand per day
- 9,500 packs
- Line capacity per day
- 6,557 packs
- Bottleneck
- Optical Soft-Berry/Color Kick
Reading the bottleneck
The bottleneck is "Optical Soft-Berry/Color Kick": it can process 6,557 packs per day against a demand of 9,500 packs, so it falls short of demand by 31.0%. Once downtime and scrap are counted, its cycle time grows from 6.1 s to 7.8 s, against a takt of 5.7 s. The largest loss at this step is equipment downtime (uptime 84%), about 1.2 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Agri-Food Harvest & Export Packhouses: Agri-Food Harvest & Export Packhouses
- Fresh Produce Optical Grading & Export Pack
- Hass Avocado Hydro-Cool & Dry-Matter Export
- Glasshouse Truss Tomato Optical Color & Pack
- Optical Defect Wash, Size & Net-Bag Potato Line
- Medjool Date Ultrasonic Mist & Window Box Line
- Triple-Wash Ready-to-Eat Baby Spinach Pillow Bag
- Laser & X-Ray Almond Hulling, Shelling & Pack
- Controlled-Atmosphere (CA) Apple Defect Line
- Living & Cut Fresh Herb Sleeve & Clamshell Line
- 2-Hr Field-to-Cooler Strawberry Punnet Line
- Sulfur-Pad Export Seedless Table Grape Pack