Fresh Produce Optical Grading & Export Pack
Product family: 15kg Export Citrus Cartons.
Flow: Orchard Grower Cooperatives → Bin Reception & Drench → Wash, Wax & Dry Tunnel → Optical Sizer & Brix Grading → Carton Fill & Cold Tunnel → Phyto QC & Container Load → EU & UK Supermarket Chains
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Bin Reception & Drench | 19.2 s | 15 min | 94% | 97.8% | 900 | 1,440 (0.80 d) | 2,499 |
| 2. Wash, Wax & Dry Tunnel | 23.4 s | 12 min | 93% | 98.4% | 720 | 1,260 (0.70 d) | 2,041 |
| 3. Optical Sizer & Brix Grading | 32.1 s | 28 min | 84% | 93.0% | 1,080 | 2,160 (1.20 d) | 1,246 |
| 4. Carton Fill & Cold Tunnel | 24.6 s | 10 min | 93% | 98.4% | 540 | 1,620 (0.90 d) | 1,934 |
| 5. Phyto QC & Container Load | 16.8 s | 8 min | 97% | 99.2% | 540 | 1,080 (0.60 d) | 3,001 |
Key figures
- Takt time
- 30.0 s
- Lead time
- 4.90 d
- Value-added time
- 116 s
- Process cycle efficiency (PCE)
- 0.044%
- Rolled throughput yield (RTY)
- 87.4%
- Customer demand per day
- 1,800 crates
- Line capacity per day
- 1,246 crates
- Bottleneck
- Optical Sizer & Brix Grading
Reading the bottleneck
The bottleneck is "Optical Sizer & Brix Grading": it can process 1,246 crates per day against a demand of 1,800 crates, so it falls short of demand by 30.8%. Once downtime and scrap are counted, its cycle time grows from 32.1 s to 41.1 s, against a takt of 30.0 s. The largest loss at this step is equipment downtime (uptime 84%), about 6.1 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Agri-Food Harvest & Export Packhouses: Agri-Food Harvest & Export Packhouses
- Hass Avocado Hydro-Cool & Dry-Matter Export
- Glasshouse Truss Tomato Optical Color & Pack
- Soft-Touch Air-Cushion Blueberry Clamshell Line
- Optical Defect Wash, Size & Net-Bag Potato Line
- Medjool Date Ultrasonic Mist & Window Box Line
- Triple-Wash Ready-to-Eat Baby Spinach Pillow Bag
- Laser & X-Ray Almond Hulling, Shelling & Pack
- Controlled-Atmosphere (CA) Apple Defect Line
- Living & Cut Fresh Herb Sleeve & Clamshell Line
- 2-Hr Field-to-Cooler Strawberry Punnet Line
- Sulfur-Pad Export Seedless Table Grape Pack