Medjool Date Ultrasonic Mist & Window Box Line
Product family: 1kg Luxury Export Dates.
Flow: Desert Palm Groves → -18°C Thermal Shock Disinfest → Vacuum Moisture Equilibration → NIR Loose-Skin & Weight Sizer → Hand/Robot Orient in Tray → Cellophane Seal & Gold Box → Middle East & EU Grocers
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. -18°C Thermal Shock Disinfest | 10.8 s | 15 min | 94% | 97.8% | 1,600 | 2,560 (0.80 d) | 4,443 |
| 2. Vacuum Moisture Equilibration | 13.2 s | 12 min | 93% | 98.4% | 1,280 | 2,240 (0.70 d) | 3,619 |
| 3. NIR Loose-Skin & Weight Sizer | 18.1 s | 28 min | 84% | 93.0% | 1,920 | 3,840 (1.20 d) | 2,210 |
| 4. Hand/Robot Orient in Tray | 13.8 s | 10 min | 93% | 98.4% | 960 | 2,880 (0.90 d) | 3,448 |
| 5. Cellophane Seal & Gold Box | 9.5 s | 8 min | 97% | 99.2% | 960 | 1,920 (0.60 d) | 5,308 |
Key figures
- Takt time
- 16.9 s
- Lead time
- 4.90 d
- Value-added time
- 65.4 s
- Process cycle efficiency (PCE)
- 0.025%
- Rolled throughput yield (RTY)
- 87.4%
- Customer demand per day
- 3,200 packs
- Line capacity per day
- 2,210 packs
- Bottleneck
- NIR Loose-Skin & Weight Sizer
Reading the bottleneck
The bottleneck is "NIR Loose-Skin & Weight Sizer": it can process 2,210 packs per day against a demand of 3,200 packs, so it falls short of demand by 30.9%. Once downtime and scrap are counted, its cycle time grows from 18.1 s to 23.2 s, against a takt of 16.9 s. The largest loss at this step is equipment downtime (uptime 84%), about 3.4 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Agri-Food Harvest & Export Packhouses: Agri-Food Harvest & Export Packhouses
- Fresh Produce Optical Grading & Export Pack
- Hass Avocado Hydro-Cool & Dry-Matter Export
- Glasshouse Truss Tomato Optical Color & Pack
- Soft-Touch Air-Cushion Blueberry Clamshell Line
- Optical Defect Wash, Size & Net-Bag Potato Line
- Triple-Wash Ready-to-Eat Baby Spinach Pillow Bag
- Laser & X-Ray Almond Hulling, Shelling & Pack
- Controlled-Atmosphere (CA) Apple Defect Line
- Living & Cut Fresh Herb Sleeve & Clamshell Line
- 2-Hr Field-to-Cooler Strawberry Punnet Line
- Sulfur-Pad Export Seedless Table Grape Pack