Diamond-Cut Flow-Formed Alloy Wheel Line

Product family: 19-Inch Lightweight Sport Wheels.

Flow: Primary aluminum ingot supplier → Low-Pressure Die Casting → Flow-Form Rim Spinning → X-Ray Pore Check & T6 Heat → Powder Base & Diamond-Cut CNC → Acrylic Clear & Imbalance QC → OEM & Tuning Retailers

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Diamond-Cut Flow-Formed Alloy Wheel LineSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Primary aluminum ingot supplier → Low-Pressure Die Casting (42.0 s) → Flow-Form Rim Spinning (45.0 s) → X-Ray Pore Check & T6 Heat (62.0 s) → Powder Base & Diamond-Cut CNC (43.0 s) → Acrylic Clear & Imbalance QC (32.4 s) → OEM & Tuning Retailers.SUPPLIERPrimaryaluminum ingotsupplierI2.40 d1Low-Pressure DieCastingC/T 42.0 sI1.80 d2Flow-Form RimSpinningC/T 45.0 sI2.10 d3X-Ray Pore Check& T6 HeatC/T 62.0 sI1.00 d4Powder Base &Diamond-Cut CNCC/T 43.0 sI0.90 d5Acrylic Clear &Imbalance QCC/T 32.4 sI2.20 dCUSTOMEROEM & TuningRetailers1,400 / parts

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Low-Pressure Die Casting42.0 s15 min94%92.5%1,4003,360 (2.40 d)1,658
2. Flow-Form Rim Spinning45.0 s20 min92%97.6%1,4002,520 (1.80 d)1,592
3. X-Ray Pore Check & T6 Heat62.0 s30 min85%94.2%1,1202,940 (2.10 d)1,017
4. Powder Base & Diamond-Cut CNC43.0 s12 min94%98.4%5601,400 (1.00 d)1,704
5. Acrylic Clear & Imbalance QC32.4 s8 min97%99.4%7001,260 (0.90 d)2,382

Key figures

Takt time
57.9 s
Lead time
10.4 d
Value-added time
224 s
Process cycle efficiency (PCE)
0.027%
Rolled throughput yield (RTY)
83.2%
Customer demand per day
1,400 parts
Line capacity per day
1,017 parts
Bottleneck
X-Ray Pore Check & T6 Heat

Reading the bottleneck

The bottleneck is "X-Ray Pore Check & T6 Heat": it can process 1,017 parts per day against a demand of 1,400 parts, so it falls short of demand by 27.4%. Once downtime and scrap are counted, its cycle time grows from 62.0 s to 77.4 s, against a takt of 57.9 s. The largest loss at this step is equipment downtime (uptime 85%), about 10.9 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.