AGM Start-Stop Lead-Acid Battery Plant

Product family: 12V 80Ah AGM Auto Batteries.

Flow: Recycled Lead Refiners → Grid Punch & Oxide Paste → Steam Cure & Envelope Stack → Cast-On-Strap & Poly Case Weld → Vacuum Acid Fill & Tank Form → Cold-Crank CCA Pulse Audit → IAM & OEM Battery Service

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: AGM Start-Stop Lead-Acid Battery PlantSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Recycled Lead Refiners → Grid Punch & Oxide Paste (18.2 s) → Steam Cure & Envelope Stack (19.7 s) → Cast-On-Strap & Poly Case Weld (27.3 s) → Vacuum Acid Fill & Tank Form (18.7 s) → Cold-Crank CCA Pulse Audit (14.2 s) → IAM & OEM Battery Service.SUPPLIERRecycled LeadRefinersI2.40 d1Grid Punch &Oxide PasteC/T 18.2 sI1.80 d2Steam Cure &Envelope StackC/T 19.7 sI2.10 d3Cast-On-Strap &Poly Case WeldC/T 27.3 sI1.00 d4Vacuum Acid Fill& Tank FormC/T 18.7 sI0.90 d5Cold-Crank CCAPulse AuditC/T 14.2 sI2.20 dCUSTOMERIAM & OEMBattery Service3,200 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Grid Punch & Oxide Paste18.2 s15 min94%92.5%3,2007,680 (2.40 d)3,827
2. Steam Cure & Envelope Stack19.7 s20 min92%97.6%3,2005,760 (1.80 d)3,637
3. Cast-On-Strap & Poly Case Weld27.3 s30 min85%94.2%2,5606,720 (2.10 d)2,310
4. Vacuum Acid Fill & Tank Form18.7 s12 min94%98.4%1,2803,200 (1.00 d)3,917
5. Cold-Crank CCA Pulse Audit14.2 s8 min97%99.4%1,6002,880 (0.90 d)5,435

Key figures

Takt time
25.3 s
Lead time
10.4 d
Value-added time
98.1 s
Process cycle efficiency (PCE)
0.012%
Rolled throughput yield (RTY)
83.2%
Customer demand per day
3,200 units
Line capacity per day
2,310 units
Bottleneck
Cast-On-Strap & Poly Case Weld

Reading the bottleneck

The bottleneck is "Cast-On-Strap & Poly Case Weld": it can process 2,310 units per day against a demand of 3,200 units, so it falls short of demand by 27.8%. Once downtime and scrap are counted, its cycle time grows from 27.3 s to 34.1 s, against a takt of 25.3 s. The largest loss at this step is equipment downtime (uptime 85%), about 4.8 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.