Heavy Commercial Manual Transmission Rebuild
Product family: 16-Speed Fleet Gearbox Reman.
Flow: Fleet Maintenance Yards → Hot-Jet Strip & Wash → Gear Tooth Mag-Particle Check → Synchro Cone & Bearing Match → Laser Shaft Shimming Stack → Loaded Noise & Shift Dyno → Trucking Operators
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Hot-Jet Strip & Wash | 694 s | 15 min | 94% | 92.5% | 28 | 67 (2.39 d) | 33 |
| 2. Gear Tooth Mag-Particle Check | 752 s | 20 min | 92% | 97.6% | 28 | 50 (1.79 d) | 31 |
| 3. Synchro Cone & Bearing Match | 1,041 s | 30 min | 85% | 94.2% | 22 | 59 (2.11 d) | 19 |
| 4. Laser Shaft Shimming Stack | 714 s | 12 min | 94% | 98.4% | 11 | 28 (1.00 d) | 33 |
| 5. Loaded Noise & Shift Dyno | 540 s | 8 min | 97% | 99.4% | 14 | 25 (0.89 d) | 46 |
Key figures
- Takt time
- 964 s
- Lead time
- 10.5 d
- Value-added time
- 3,741 s
- Process cycle efficiency (PCE)
- 1.3%
- Rolled throughput yield (RTY)
- 83.2%
- Customer demand per day
- 28 units
- Line capacity per day
- 19 units
- Bottleneck
- Synchro Cone & Bearing Match
Reading the bottleneck
The bottleneck is "Synchro Cone & Bearing Match": it can process 19 units per day against a demand of 28 units, so it falls short of demand by 32.1%. Once downtime and scrap are counted, its cycle time grows from 1,041 s to 1,300 s, against a takt of 964 s. The largest loss at this step is equipment downtime (uptime 85%), about 184 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Aftermarket & Remanufacturing: Aftermarket & Remanufacturing
- Remanufactured 180A Smart Alternator Line
- VNT Remanufactured Passenger Turbocharger
- Heavy Fleet Cold-Cure Pre-Molded Tire Retread
- Diamond-Cut Flow-Formed Alloy Wheel Line
- Copper-Free Ceramic Disc Brake Pad Press
- Gas-Pressurized Monotube Shock Absorber
- Heavy-Duty Aluminum Radiator Brazing Line
- End-of-Life Catalytic Converter PGM Recovery
- AGM Start-Stop Lead-Acid Battery Plant
- ARG Aftermarket Replacement Windshield Cell
- Spin-On Engine Oil Filter High-Speed Line