Heavy Fleet Cold-Cure Pre-Molded Tire Retread
Product family: Class-8 Drive Axle Retreads.
Flow: Fleet casing supplier → Shearography Laser Inspect → Rotary Rasp Buffer Crown → Extrude Cushion & Tread Band → Envelope & Pressure Cure Chamber → Final Buff & Tire Stamp QC → Commercial Transport Fleets
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Shearography Laser Inspect | 60.0 s | 15 min | 94% | 92.5% | 650 | 1,560 (2.40 d) | 770 |
| 2. Rotary Rasp Buffer Crown | 65.0 s | 20 min | 92% | 97.6% | 650 | 1,170 (1.80 d) | 729 |
| 3. Extrude Cushion & Tread Band | 90.0 s | 30 min | 85% | 94.2% | 520 | 1,365 (2.10 d) | 460 |
| 4. Envelope & Pressure Cure Chamber | 61.0 s | 12 min | 94% | 98.4% | 260 | 650 (1.00 d) | 792 |
| 5. Final Buff & Tire Stamp QC | 47.0 s | 8 min | 97% | 99.4% | 325 | 585 (0.90 d) | 1,088 |
Key figures
- Takt time
- 83.1 s
- Lead time
- 10.4 d
- Value-added time
- 323 s
- Process cycle efficiency (PCE)
- 0.057%
- Rolled throughput yield (RTY)
- 83.2%
- Customer demand per day
- 650 units
- Line capacity per day
- 460 units
- Bottleneck
- Extrude Cushion & Tread Band
Reading the bottleneck
The bottleneck is "Extrude Cushion & Tread Band": it can process 460 units per day against a demand of 650 units, so it falls short of demand by 29.2%. Once downtime and scrap are counted, its cycle time grows from 90.0 s to 112 s, against a takt of 83.1 s. The largest loss at this step is equipment downtime (uptime 85%), about 15.9 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Aftermarket & Remanufacturing: Aftermarket & Remanufacturing
- Remanufactured 180A Smart Alternator Line
- VNT Remanufactured Passenger Turbocharger
- Diamond-Cut Flow-Formed Alloy Wheel Line
- Copper-Free Ceramic Disc Brake Pad Press
- Gas-Pressurized Monotube Shock Absorber
- Heavy-Duty Aluminum Radiator Brazing Line
- End-of-Life Catalytic Converter PGM Recovery
- AGM Start-Stop Lead-Acid Battery Plant
- ARG Aftermarket Replacement Windshield Cell
- Heavy Commercial Manual Transmission Rebuild
- Spin-On Engine Oil Filter High-Speed Line