Copper-Free Ceramic Disc Brake Pad Press
Product family: ECE R90 Aftermarket Pad Sets.
Flow: Friction Raw Compounds → Backplate Grit & Adhesive → Positive Hot-Mold Cure Press → 300°C Scorching Plate Bake → Chamfer Slot & Noise Shim → Shear Strength & Box Shrink → Retail Auto Chains
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Backplate Grit & Adhesive | 9.3 s | 15 min | 94% | 92.5% | 4,200 | 10,080 (2.40 d) | 4,965 |
| 2. Positive Hot-Mold Cure Press | 10.0 s | 20 min | 92% | 97.6% | 4,200 | 7,560 (1.80 d) | 4,741 |
| 3. 300°C Scorching Plate Bake | 13.9 s | 30 min | 85% | 94.2% | 3,360 | 8,820 (2.10 d) | 2,981 |
| 4. Chamfer Slot & Noise Shim | 9.5 s | 12 min | 94% | 98.4% | 1,680 | 4,200 (1.00 d) | 5,082 |
| 5. Shear Strength & Box Shrink | 7.2 s | 8 min | 97% | 99.4% | 2,100 | 3,780 (0.90 d) | 7,103 |
Key figures
- Takt time
- 12.9 s
- Lead time
- 10.4 d
- Value-added time
- 49.9 s
- Process cycle efficiency (PCE)
- 0.009%
- Rolled throughput yield (RTY)
- 83.2%
- Customer demand per day
- 4,200 packs
- Line capacity per day
- 2,981 packs
- Bottleneck
- 300°C Scorching Plate Bake
Reading the bottleneck
The bottleneck is "300°C Scorching Plate Bake": it can process 2,981 packs per day against a demand of 4,200 packs, so it falls short of demand by 29.0%. Once downtime and scrap are counted, its cycle time grows from 13.9 s to 17.4 s, against a takt of 12.9 s. The largest loss at this step is equipment downtime (uptime 85%), about 2.5 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Aftermarket & Remanufacturing: Aftermarket & Remanufacturing
- Remanufactured 180A Smart Alternator Line
- VNT Remanufactured Passenger Turbocharger
- Heavy Fleet Cold-Cure Pre-Molded Tire Retread
- Diamond-Cut Flow-Formed Alloy Wheel Line
- Gas-Pressurized Monotube Shock Absorber
- Heavy-Duty Aluminum Radiator Brazing Line
- End-of-Life Catalytic Converter PGM Recovery
- AGM Start-Stop Lead-Acid Battery Plant
- ARG Aftermarket Replacement Windshield Cell
- Heavy Commercial Manual Transmission Rebuild
- Spin-On Engine Oil Filter High-Speed Line