ARG Aftermarket Replacement Windshield Cell

Product family: Aftermarket Acoustic Windshields.

Flow: Float raw-glass supplier → CNC Shape Cut & Seaming → Black Frit Silkscreen Print → Press-Bend Roller Furnace → De-Air Bag & Autoclave → Optical Distortion & Camera Pad → Auto-Glass Fitting Networks

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: ARG Aftermarket Replacement Windshield CellSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Float raw-glass supplier → CNC Shape Cut & Seaming (52.0 s) → Black Frit Silkscreen Print (56.0 s) → Press-Bend Roller Furnace (78.0 s) → De-Air Bag & Autoclave (53.0 s) → Optical Distortion & Camera Pad (40.0 s) → Auto-Glass Fitting Networks.SUPPLIERFloat raw-glasssupplierI2.40 d1CNC Shape Cut &SeamingC/T 52.0 sI1.80 d2Black FritSilkscreen PrintC/T 56.0 sI2.10 d3Press-Bend RollerFurnaceC/T 78.0 sI1.00 d4De-Air Bag &AutoclaveC/T 53.0 sI0.90 d5OpticalDistortion &…C/T 40.0 sI2.20 dCUSTOMERAuto-GlassFitting…750 / parts

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. CNC Shape Cut & Seaming52.0 s15 min94%92.5%7501,800 (2.40 d)888
2. Black Frit Silkscreen Print56.0 s20 min92%97.6%7501,350 (1.80 d)847
3. Press-Bend Roller Furnace78.0 s30 min85%94.2%6001,575 (2.10 d)531
4. De-Air Bag & Autoclave53.0 s12 min94%98.4%300750 (1.00 d)911
5. Optical Distortion & Camera Pad40.0 s8 min97%99.4%375675 (0.90 d)1,279

Key figures

Takt time
72.0 s
Lead time
10.4 d
Value-added time
279 s
Process cycle efficiency (PCE)
0.050%
Rolled throughput yield (RTY)
83.2%
Customer demand per day
750 parts
Line capacity per day
531 parts
Bottleneck
Press-Bend Roller Furnace

Reading the bottleneck

The bottleneck is "Press-Bend Roller Furnace": it can process 531 parts per day against a demand of 750 parts, so it falls short of demand by 29.2%. Once downtime and scrap are counted, its cycle time grows from 78.0 s to 97.4 s, against a takt of 72.0 s. The largest loss at this step is equipment downtime (uptime 85%), about 13.8 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.