End-of-Life Catalytic Converter PGM Recovery

Product family: Platinum & Palladium Refining.

Flow: ELV Auto Dismantlers → Pneumatic Shell Decanning → Hammer-Mill Brick Pulverize → Rotary Blending & XRF Assay → Super-Sack Vacuum Lot Seal → ICP-OES Smelter Release → Precious Metal Refineries

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: End-of-Life Catalytic Converter PGM RecoverySupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. ELV Auto Dismantlers → Pneumatic Shell Decanning (41.0 s) → Hammer-Mill Brick Pulverize (44.0 s) → Rotary Blending & XRF Assay (61.0 s) → Super-Sack Vacuum Lot Seal (42.0 s) → ICP-OES Smelter Release (31.8 s) → Precious Metal Refineries.SUPPLIERELV AutoDismantlersI2.40 d1Pneumatic ShellDecanningC/T 41.0 sI1.80 d2Hammer-Mill BrickPulverizeC/T 44.0 sI2.10 d3Rotary Blending &XRF AssayC/T 61.0 sI1.00 d4Super-Sack VacuumLot SealC/T 42.0 sI0.90 d5ICP-OES SmelterReleaseC/T 31.8 sI2.20 dCUSTOMERPrecious MetalRefineries950 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Pneumatic Shell Decanning41.0 s15 min94%92.5%9502,280 (2.40 d)1,126
2. Hammer-Mill Brick Pulverize44.0 s20 min92%97.6%9501,710 (1.80 d)1,078
3. Rotary Blending & XRF Assay61.0 s30 min85%94.2%7601,995 (2.10 d)679
4. Super-Sack Vacuum Lot Seal42.0 s12 min94%98.4%380950 (1.00 d)1,150
5. ICP-OES Smelter Release31.8 s8 min97%99.4%475855 (0.90 d)1,608

Key figures

Takt time
56.8 s
Lead time
10.4 d
Value-added time
220 s
Process cycle efficiency (PCE)
0.039%
Rolled throughput yield (RTY)
83.2%
Customer demand per day
950 units
Line capacity per day
679 units
Bottleneck
Rotary Blending & XRF Assay

Reading the bottleneck

The bottleneck is "Rotary Blending & XRF Assay": it can process 679 units per day against a demand of 950 units, so it falls short of demand by 28.5%. Once downtime and scrap are counted, its cycle time grows from 61.0 s to 76.2 s, against a takt of 56.8 s. The largest loss at this step is equipment downtime (uptime 85%), about 10.8 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.